BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Four workers can dig a ditch in 42 days. They begin

Expert replies
by emdadul28 » Sun Dec 04, 2016 6:00 pm
Four workers can dig a ditch in 42 days. They begin the work, but one worker work only 12 days. How long will it take to complete the job?
A contract is to be completed in 56 days and 104 men were set to work, each working 8 hours a day. After 30 days, 2/5 of the work is completed. How many additional men be employed, so that the work may be completed in time if each man works 9 hours a day?
Can anyone help with these two math by following same procedure. Thank in advance.
Join the discussion
Source: — Problem Solving |

by GMATGuruNY » Mon Dec 05, 2016 4:14 am
Moving forward, please post each question in a separate thread.
There is typo in the first problem.
It should read as follows:
emdadul28 wrote:
Four workers can dig a ditch in 42 days. They begin the work, but one worker works only 1/2 days. How long will it take to complete the job?
Let the rate for each full-time worker = 2 units per day, implying that the rate for 4 full-time workers = 4*2 = 8 units per day.
In 42 days, the amount of work produced by 4 full-time workers = rt = 8*42 = 336 units.
Rate for 3 full-time workers and 1 half-time worker = (3*2 + 1) = 7 units per day.
To produce 336 units, the time required by 3 full-time workers and 1 half-time worker = w/r = 336/7 = 48 days.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by GMATGuruNY » Mon Dec 05, 2016 5:12 am
I believe that the following reflects the intent of the problem:
A job is to be completed by 104 men, each working at a constant rate for 8 hours per day. After 30 days, 2/5 of the job is completed. If each man increases his time per day to 9 hours, how many additional men must be employed to complete the remainder of the job in 26 days?
We can use the following formula:

(number of workers)(hours per day)(number of days)/output = (number of workers)(hours per day)(number of days)/output

Let the job = 5 units, implying that 2 of the units are completed in the first 30 days and that the remaining 3 units must be produced in the final 26 days.
Let x = the number of workers required to produce the remaining 3 units in 26 days.

104 men working 8 hours per day for 30 days produce 2 units.
We want to determine how many workers are required to produce 3 units in 26 days if the number of hours per day is increased to 9.
Plugging these values into the formula above, we get:

(104)(8)(30)/2 = (x)(9)(26)/3

Solving the resulting equation, we get:
x = 160.

Since the number of workers must increase from 104 to 160, the number of additional workers = 160-104 = 56.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by Matt@VeritasPrep » Thu Dec 08, 2016 8:28 pm
emdadul28 wrote:Four workers can dig a ditch in 42 days. They begin the work, but one worker work only 12 days. How long will it take to complete the job?
I'm not sure there's a typo here, as the answer is still a round number.

4 workers * 42 days = 168 man-days of work

If the four workers work together for 12 days, they complete 4 * 12 = 48 man-days of work.

That means that 120 man-days are left. 120 man-days / 3 remaining workers = 40 days.

So the job will take 52 days, assuming everyone works each day without taking days off (except for our fourth worker, who disappears after the twelfth day).
Join the discussion

by Matt@VeritasPrep » Thu Dec 08, 2016 8:33 pm
emdadul28 wrote:A contract is to be completed in 56 days and 104 men were set to work, each working 8 hours a day. After 30 days, 2/5 of the work is completed. How many additional men be employed, so that the work may be completed in time if each man works 9 hours a day?
30 days * 8 hours = 240 hours

240 hours * 104 men = 24960 man-hours

If 24960 man-hours = (2/5) of the job, then the job = 62400 man-hours total.

Since we've done 24960, we have 37440 hours left to do.

If we have men working at 9 hours a day, that's 37440 / 9 = 4160 man-days left.

We have 26 actual days, so we need 4160 / 26 = 160 men to finish the job in time. We already have 104, so we need to hire 56 more.
Join the discussion

by Matt@VeritasPrep » Thu Dec 08, 2016 8:33 pm
And a tip of the cap to the author of the second question: it was very clever to have the extra number of men turn out to be the same as the number of days!
Join the discussion

by Arunkumar S » Sun Dec 18, 2016 11:05 am
Always assume total work is 1
4 worker complete work in 42 days
So 1 workers 1 day work is 1/(42*4)=1/168
12(n1) days works for 4 workers is = 4*(1/168)*12 ==> 12/42 ==> 2/7
Balance work = 1-(2/7)= 5/7
1 worker left after 12 days So now we have only 3 workers and 3 workers one day job is 3*(1/168)= 1/56
5/7 = n2*(1/56) ==> n2 = (5/7)*56 =40
So total no of days n =n1+n2
n = 12+40 = 52
Ans = 52
Join the discussion