Sam and David agreed to complete a work in 14 days. They also agreed to forfeit thrice the amount of wages corresponding to the unfinished if they failed to complete the work in 14 days. As they could not complete the work in 14 days, they lost 3/8th of the amount that they would have together received had they completed the work in time. If Sam alone can complete the work in 80 days,the time that David alone would take to complete the work is
A. 20 days
B. 24 days
C. 30 days
D. 35 days
E. 40 days
I'm confused how to set up the formulas here. Can any experts help?