BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Sam and David agreed to complete a work in 14 days. They als

Expert replies
by BTGmoderatorAT » Sun Nov 19, 2017 5:24 am
Sam and David agreed to complete a work in 14 days. They also agreed to forfeit thrice the amount of wages corresponding to the unfinished if they failed to complete the work in 14 days. As they could not complete the work in 14 days, they lost 3/8th of the amount that they would have together received had they completed the work in time. If Sam alone can complete the work in 80 days,the time that David alone would take to complete the work is

A. 20 days
B. 24 days
C. 30 days
D. 35 days
E. 40 days

I'm confused how to set up the formulas here. Can any experts help?
Join the discussion
Source: — Problem Solving |

by Jeff@TargetTestPrep » Wed Nov 22, 2017 12:21 pm
ardz24 wrote:Sam and David agreed to complete a work in 14 days. They also agreed to forfeit thrice the amount of wages corresponding to the unfinished if they failed to complete the work in 14 days. As they could not complete the work in 14 days, they lost 3/8th of the amount that they would have together received had they completed the work in time. If Sam alone can complete the work in 80 days,the time that David alone would take to complete the work is

A. 20 days
B. 24 days
C. 30 days
D. 35 days
E. 40 days
Since they lost 3/8 of the amount that they would have together received had they completed the job on time and they actually forfeited thrice the amount of wages corresponding to the unfinished, we can relate these two quantities as: ⅜ = 3x, and so x = ⅛, which means that they only had 1/8 of the job unfinished. In other words, they finished 7/8 of the job.

We can let n = the number of days David would take to complete the work alone. We are given that Sam would take 80 days to complete the work alone; thus, his rate would be 1/80, and David's rate would be 1/n. Since they both worked 14 days, and they finished 7/8 of the job, we can create the following equation:

14 x 1/80 + 14 x 1/n = 7/8

14/80 + 14/n = 7/8

Multiply the equation by 80n we have:

14n + 1120 = 70n

1120 = 56n

n = 1120/56 = 20

Answer: A