stephkhaira wrote:Each of 10 machines works at the same constant rate. Together they complete a job in 16 hours. How many hous does it take 8 machines to finish the job?

18
20
22
24
26

[spoiler]ans: 20[/spoiler]
Hi Stephkhaira,
Given: 10 machine takes 16 hours to complete a certain job.
To Find: How many hour does it take to complete same job using 8 machines.

Note: For these kind of problem we need to imagine some value( for example, here each machine produce one unit per hour)

Solution:
Ok, Let's imagine each machine produce One unit per hour.
therefore, 10*1*16=160.
So 10 machines produce 160 units of total in 16 hours.

Let X be no of hours for 8 machines to produce 160 Units.
In the same rate,
8*1*X =160

Hence X = 20

Regards,
Uva.

GMAT/MBA Expert

User avatar
Elite Legendary Member
Posts: 10392
Joined: Sun Jun 23, 2013 6:38 pm
Location: Palo Alto, CA
Thanked: 2867 times
Followed by:511 members
GMAT Score:800

by [email protected] » Mon Aug 26, 2013 9:32 pm
Hi stephkhaira,

Uva has explained a great, straight-forward approach to this question (it's the same way that I would solve this problem), so it's worth knowing.

As an aside, there's also a "ratio pattern" that's worth knowing:

You'll notice that in this question, the number of machines drops from 10 to 8; this is a 20% decrease. To end up with the same total output (in this case, the completed job), the way to offset the 20% decrease in machines is with a 25% increase in the other variable (in this case, the number of hours).

We start with 16 hours per machine; increasing this by 25% = 16 + 4 = 20 hours per machine.

GMAT assassins aren't born, they're made,
Rich
Contact Rich at [email protected]
Image

User avatar
Legendary Member
Posts: 643
Joined: Wed Aug 14, 2013 4:27 am
Thanked: 48 times
Followed by:7 members

by vinay1983 » Wed Aug 28, 2013 6:47 am
I usually use the proportion method.

10 machines take 16 hours, 8 machines will take?

Notice that the no. of machines required for completion of the work have reduced, hence the no. of hours required will be more(Inverse proportion)

Machines time in hours

10 16


8 x

I.e x/16=10/8

x= 10/8*16=20

Hope this helps!
You can, for example never foretell what any one man will do, but you can say with precision what an average number will be up to!

User avatar
Master | Next Rank: 500 Posts
Posts: 283
Joined: Sun Jun 23, 2013 11:56 pm
Location: Bangalore, India
Thanked: 97 times
Followed by:26 members
GMAT Score:750

by ganeshrkamath » Wed Aug 28, 2013 10:21 am
stephkhaira wrote:Each of 10 machines works at the same constant rate. Together they complete a job in 16 hours. How many hous does it take 8 machines to finish the job?

18
20
22
24
26

[spoiler]ans: 20[/spoiler]
Let each machine take M hours to complete the work alone.
Rate of each machine = 1/M per hour
Rate of 10 machines = 10/M per hour
So the machines take M/10 hours to complete the work = 16 hours
M = 160

So 8 machines can finish the job in M/8 = 160/8 = 20 hours

Choose B

Cheers
Every job is a self-portrait of the person who did it. Autograph your work with excellence.

Kelley School of Business (Class of 2016)
GMAT Score: 750 V40 Q51 AWA 5 IR 8
https://www.beatthegmat.com/first-attemp ... tml#688494