Rate of work

This topic has expert replies
User avatar
Senior | Next Rank: 100 Posts
Posts: 56
Joined: Wed Sep 01, 2010 10:04 am
Thanked: 1 times
Followed by:20 members

Rate of work

by Akansha » Mon May 23, 2011 9:35 pm
X and Y work at constant rates, how many more hours does it take machine y,
alone, to fill an order of a certain size than machine X alone.
a. X and Y together fill order in 2�3 the time that X alone does
b. Y alone does it in twice the time as X alone does

OA is E

I selected the correct option but I wanted to get an explanation to understand such type of problems better.
Source: — Data Sufficiency |

Legendary Member
Posts: 1448
Joined: Tue May 17, 2011 9:55 am
Location: India
Thanked: 375 times
Followed by:53 members

by Frankenstein » Mon May 23, 2011 10:22 pm
Let the work rates of X and Y be x and y respectively

From(1) : (x+y).(2t/3) = x.(t) => x=2y.
We can compare the work rates but we do not know the absolute time required by either of machines.
Insufficient

From(2) : y.(2t) = x.(t) => x=2y. Similar to (1), we need absolute time required to finish the job by at least one f the machines to calculate that of the other.
Insufficient

(1) and (2) gives rise to the same condition. So, even combining (1) and (2), we do not arrive at the answer
Insufficient

Hence, answer E.

Cheers!

GMAT/MBA Expert

User avatar
GMAT Instructor
Posts: 3835
Joined: Fri Apr 02, 2010 10:00 pm
Location: Milpitas, CA
Thanked: 1854 times
Followed by:523 members
GMAT Score:770

by Anurag@Gurome » Mon May 23, 2011 10:26 pm
Akansha wrote:X and Y work at constant rates, how many more hours does it take machine y,
alone, to fill an order of a certain size than machine X alone.
a. X and Y together fill order in 2�3 the time that X alone does
b. Y alone does it in twice the time as X alone does

OA is E

I selected the correct option but I wanted to get an explanation to understand such type of problems better.
Let the rate at which machine X works be A, and the rate at which machine Y works = B
1 hr work of machine X = 1/A and 1 hr work of machine Y = 1/B
1/Total time taken by both machines = 1/A + 1/B or Total time taken by both machines = AB/(A + B)

(1) X and Y together fill order in 2�3 the time that X alone does implies AB/(A + B) = 2A/3
3B = 2A + 2B or B = 2A, but we don't get to know the exact values.
So, (1) is NOT SUFFICIENT.

(2) B = 2A, which again is NOT SUFFICIENT.

Combining (1) and (2) also does not provide any new information, as both the statements give the same info.

The correct answer is E.
Anurag Mairal, Ph.D., MBA
GMAT Expert, Admissions and Career Guidance
Gurome, Inc.
1-800-566-4043 (USA)

Join Our Facebook Groups
GMAT with Gurome
https://www.facebook.com/groups/272466352793633/
Admissions with Gurome
https://www.facebook.com/groups/461459690536574/
Career Advising with Gurome
https://www.facebook.com/groups/360435787349781/

User avatar
Master | Next Rank: 500 Posts
Posts: 436
Joined: Tue Feb 08, 2011 3:07 am
Thanked: 72 times
Followed by:6 members

by manpsingh87 » Mon May 23, 2011 10:27 pm
Akansha wrote:X and Y work at constant rates, how many more hours does it take machine y,
alone, to fill an order of a certain size than machine X alone.
a. X and Y together fill order in 2�3 the time that X alone does
b. Y alone does it in twice the time as X alone does

OA is E

I selected the correct option but I wanted to get an explanation to understand such type of problems better.
let x works for p hours, and y works for q hours to finish the job;

let the no. of units of job to be done is p*q units;

therefore in 1 hour x will do p*q/p=q units;
and y will do p*q/q=p units;

1) no. of units that x and y will do while working together=p*q/p+q;

now as per the condition we have;
p*q/(p+q)= (2/3)q;
3/2p= p+q;
p=2q;
i.e. y will take twice the time taken by x in completing the job; now since we don't know about the time taken by x in completing the task hence 1 alone is not sufficient to answer the question.

2) p=2q;

which we have proved in last condition, as no new information is provided about the no. of hours taken by x to complete the job hence 2 alone is also not sufficient to answer the question.

combining 1 and 2; no new information is available hence answer should be E
O Excellence... my search for you is on... you can be far.. but not beyond my reach!

Master | Next Rank: 500 Posts
Posts: 114
Joined: Mon Sep 22, 2008 3:51 am
Thanked: 8 times
GMAT Score:680

by Fiver » Wed May 25, 2011 5:19 am
Akansha wrote:X and Y work at constant rates, how many more hours does it take machine y,
alone, to fill an order of a certain size than machine X alone.
a. X and Y together fill order in 2�3 the time that X alone does
b. Y alone does it in twice the time as X alone does

OA is E

I selected the correct option but I wanted to get an explanation to understand such type of problems better.
For people who are less inclined towards deriving formulae, here's something that has worked for me, especially to tackle such DS questions.

The question asks for an absolute value- how many more hours does it take...?

Both the answer stems are talking about a ratio; infact both the answers stems are talking about the same ratio. Hence it takes not more than 20 secs to rightly mark E as an option.