Work and time 2

by eaakbari » Thu Apr 01, 2010 10:08 pm
A can do a piece of work n 7 days of 9 hours each and B alone can do it in 6 days of 7 hours each. How long will they take to do it working together 8 2/5 hours a day?



No answer choices as its from a prep review book
Source: — Problem Solving |

User avatar
Master | Next Rank: 500 Posts
Posts: 435
Joined: Mon Mar 15, 2010 6:15 am
Thanked: 32 times
Followed by:1 members

by eaakbari » Thu Apr 01, 2010 10:11 pm
A can complete the work in (7*9)=63 hours
B can complete the work in (6*7)=42 hours
=> A's one hour's work=1/63 and
B's one hour work=1/42
(A+B)'s one hour work=1/63+1/42=5/126
Therefore, Both can finish the work in 126/5 hours.
Number of days of 8 2/5 hours each=(126*5/(5*42))=3days

Legendary Member
Posts: 610
Joined: Fri Jan 15, 2010 12:33 am
Thanked: 47 times
Followed by:2 members

by kstv » Fri Apr 02, 2010 3:54 am
A can do a piece of work in 7 days of 9 hours each and B alone can do it in 6 days of 7 hours each. How long will they take to do it working together 8 2/5 hours a day?
the question has number with factors of 3 , 2 , 7 repeatedly. So it is better not to solve them at each step
A does in 1 hr 1/ (7*9) B does in 1 hr 1/(6*7)
A + B together in 1 hr 2+3 /(7*9*2)
so in 42/5 hrs = 7*9*2*5/ 6*7*5
= 3`