Yes thanks guys this was a tricky problem but u need to use algebrac manipulation. Since it stated worker A worked for 5 days and worker B worked for 7 days and worker C worked for 13 days, 5A + 7B +13C= 1 work Since A+ B together took 20 days their combined rates= (1/20) Since B+C together took six...
- by mshrest01
Mon Jul 21, 2014 4:11 pm- Forum: Quantitative Reasoning
- Topic: Rates
- Replies: 4
- Views: 2560
Rates
If worker A and B completes in 20 days. Worker B and C completes in 16 days. Knowing that worker A worked for 5 days, worker B worked for 7 days and worker C worked for 13 days. How long is worker C going to take to complete the work alone?
- by mshrest01
Sat Jun 28, 2014 11:36 pm- Forum: Quantitative Reasoning
- Topic: Rates
- Replies: 4
- Views: 2560