work problem

This topic has expert replies
Senior | Next Rank: 100 Posts
Posts: 65
Joined: Wed Mar 26, 2014 6:56 am
Followed by:1 members

work problem

by lukaswelker » Tue Apr 01, 2014 1:12 am
here is the question

Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the job in 8 days?

2;3;4;6;8

I know the work formula but I can't seem to apply it properly.

Let me know
Cheers
Lukas
Source: — Problem Solving |

User avatar
GMAT Instructor
Posts: 15539
Joined: Tue May 25, 2010 12:04 pm
Location: New York, NY
Thanked: 13060 times
Followed by:1906 members
GMAT Score:790

by GMATGuruNY » Tue Apr 01, 2014 2:02 am
Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the job in 8 days?

2
3
4
6
8
Approach 1: Plug in a rate for EACH MACHINE

Let the rate for each machine = 1 unit per day.
Rate for 6 machines = 6 units per day.
In 12 days, the amount of work produced by 6 machines = r*t = 6*12 = 72 units.
To produce 72 units in 8 days, the required amount of work per day = w/t = 72/8 = 9 units per day.
To increase the rate from 6 units per day to 9 units per day, 3 more machines are needed.

The correct answer is B.

Approach 2: Inverse proportion method

The number of machines is INVERSELY PROPORTIONAL to the number of days:
(machines)(days) = (machines)(days).
As the number of machines INCREASES, the number of days must DECREASE, so that in each case the SAME AMOUNT OF WORK is produced.

Since 6 machines take 12 days, and the job is to be completed in 8 days, we get:
6 * 12 = m * 8
72 = 8m
m = 9.

Since 9 machines are required, the original number of machines -- 6 -- must increase by 3.

The correct answer is B.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3

GMAT/MBA Expert

User avatar
GMAT Instructor
Posts: 16207
Joined: Mon Dec 08, 2008 6:26 pm
Location: Vancouver, BC
Thanked: 5254 times
Followed by:1268 members
GMAT Score:770

by Brent@GMATPrepNow » Tue Apr 01, 2014 7:31 am
6 machines, each working at same constant rate, together can complete the job in 12 days. How many additional machines, each working at same constant rate, will be needed to complete job in 8 days?

A 3
B 4
C 5
D 6
E 2
If 6 machines take 12 days to complete the job, then we can say that the job takes 72 "machine days" to complete (6 x 12 = 72)

To complete the job in 8 days would require 9 machines (72 machine days divided by 8 days)

So, we need an additional 3 machines.

Answer = A

Cheers,
Brent
Brent Hanneson - Creator of GMATPrepNow.com
Image

User avatar
Master | Next Rank: 500 Posts
Posts: 359
Joined: Wed Mar 11, 2009 4:37 am
Location: Kolkata, India
Thanked: 50 times
Followed by:2 members

by Abhishek009 » Wed Apr 02, 2014 11:13 am
lukaswelker wrote:Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the job in 8 days?
Let the efficiency of the workers be " E " , so the total work done by the 6 machines in 12 days is -

6 * E * 12


Given the situation we need to find additional machines , let it be 6 + A

So , 6 * E * 12 = (6 + A ) * E * 8

or, 72 = 48 + 8A

or, 24 = 8A

Or, A = 3


So 3 additional machines are required....
Abhishek