BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

6 Machines

Expert replies
Source: — Problem Solving |

by Brent@GMATPrepNow » Sat Sep 28, 2013 3:40 pm
6 machines working at a constant rate can complete a job in 12 days. How many additional machines working at the same constant rate are needed to complete the job in 8 days?

A) 2
B) 3
C) 4
D) 6
E) 8


If 6 machines take 12 days to complete the job, then we can say that the job takes 72 "machine days" to complete the job (6x12=72)

To complete the job in 8 days would require 9 machines (72 machine days divided by 8)

So, we need an additional 3 machines.

Answer = B

Cheers,
Brent
Brent Hanneson - Creator of GMATPrepNow.com
Image
Join the discussion

by theCodeToGMAT » Sat Sep 28, 2013 7:56 pm
Work of 6 Machines = Rate x Time = 6 x 12 = 72

Work of N Machines = N x 8

Since total work is same so equating:
72 = N x 8 ==> 9
Additional Machines 9 - 6 = 3
Answer [spoiler]{B}[/spoiler]
R A H U L
Join the discussion

by vinay1983 » Sat Sep 28, 2013 10:14 pm
No.of machines is inversely proportional to the no. of days required

More machines less days

so

12/8*6= 9 machines in total are required so additional machines required are 9-6=3

B