work efficiency

This topic has expert replies
Legendary Member
Posts: 2326
Joined: Mon Jul 28, 2008 3:54 am
Thanked: 173 times
Followed by:2 members
GMAT Score:710

work efficiency

by gmatmachoman » Thu Apr 29, 2010 4:14 am
12 persons can do a work in 10 days working 8 hours a day. How many days will be required by 10 persons, who will work 6
hours a day. The efficiency of each of these 10 persons is twice that of the earlier persons.
Source: — Problem Solving |

Legendary Member
Posts: 576
Joined: Sat Mar 13, 2010 8:31 pm
Thanked: 97 times
Followed by:1 members

by liferocks » Thu Apr 29, 2010 4:27 am
total amount of work 12*8*10=960 man-hours

10 person complete 10*6*2 or 120 man-hour work in one day
hence they will need 960/120 or 8 days to complete the work

Ans 8 days
"If you don't know where you are going, any road will get you there."
Lewis Carroll