working on the project

This topic has expert replies
User avatar
GMAT Instructor
Posts: 3650
Joined: Wed Jan 21, 2009 4:27 am
Location: India
Thanked: 267 times
Followed by:80 members
GMAT Score:760

working on the project

by sanju09 » Tue Apr 05, 2011 4:52 am
A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?
(A) 12
(B) 16
(C) 18
(D) 26
(E) 27
The mind is everything. What you think you become. -Lord Buddha



Sanjeev K Saxena
Quantitative Instructor
The Princeton Review - Manya Abroad
Lucknow-226001

www.manyagroup.com
Source: — Problem Solving |

Legendary Member
Posts: 586
Joined: Tue Jan 19, 2010 4:38 am
Thanked: 31 times
Followed by:5 members
GMAT Score:730

by rohu27 » Tue Apr 05, 2011 5:07 am
let xbe the total number of days to complete the work.
rate of a=1/20
rate of B=1/30
so A leaves x-10 days before, in x-10 days A does x-10/20 th work.
in x days B does x/30th work.
the total shud be equal to 1 project.
so x-10/20+x/30=1.
on solving x=18

GMAT/MBA Expert

User avatar
GMAT Instructor
Posts: 3835
Joined: Fri Apr 02, 2010 10:00 pm
Location: Milpitas, CA
Thanked: 1854 times
Followed by:523 members
GMAT Score:770

by Anurag@Gurome » Tue Apr 05, 2011 5:07 am
sanju09 wrote:A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?
(A) 12
(B) 16
(C) 18
(D) 26
(E) 27
1 day work of A and B = 1/20 and 1/30 respectively.
Let the project is completed in N days.
Then B worked for all N days, and A worked for (N - 10) days.
This means A's contribution in the project = (N - 10)/20
B's contribution in the project = N/30
So, (N - 10)/20 + N/30 = 1 implies 3N - 30 + 2N = 60 or N = 18

The correct answer is C.
Anurag Mairal, Ph.D., MBA
GMAT Expert, Admissions and Career Guidance
Gurome, Inc.
1-800-566-4043 (USA)

Join Our Facebook Groups
GMAT with Gurome
https://www.facebook.com/groups/272466352793633/
Admissions with Gurome
https://www.facebook.com/groups/461459690536574/
Career Advising with Gurome
https://www.facebook.com/groups/360435787349781/

User avatar
Legendary Member
Posts: 582
Joined: Tue Mar 08, 2011 12:48 am
Thanked: 61 times
Followed by:6 members
GMAT Score:740

by force5 » Tue Apr 05, 2011 5:22 am
Hi anurag... i have a different point of view please correct ...

A and B together can complete the work in 12 days. (1/20+1/30)
now A left 10 days before which means A and B virtually worked for only 2 days.
Work done in 2 days =1/12*2=1/6
remaining work = 5/6 is done alone by B
hence time taken by B should be 25days
total time taken 25+2= 27 days.

In the solution given you have mentioned B's contribution in the project is N/30 (please see that initially both worked together hence that cannot be B's contribution).

Please correct me if im wrong.

GMAT/MBA Expert

User avatar
GMAT Instructor
Posts: 3835
Joined: Fri Apr 02, 2010 10:00 pm
Location: Milpitas, CA
Thanked: 1854 times
Followed by:523 members
GMAT Score:770

by Anurag@Gurome » Tue Apr 05, 2011 5:29 am
force5 wrote:Hi anurag... i have a different point of view please correct ...

A and B together can complete the work in 12 days. (1/20+1/30)
now A left 10 days before which means A and B virtually worked for only 2 days.
Work done in 2 days =1/12*2=1/6
remaining work = 5/6 is done alone by B
hence time taken by B should be 25days
total time taken 25+2= 27 days.

In the solution given you have mentioned B's contribution in the project is N/30 (please see that initially both worked together hence that cannot be B's contribution).

Please correct me if im wrong.
First, how can we say that A and B together can complete the work in 12 days? (1/20 + 1/30) gives us 1 day work of (A + B) together. But we don't know for how long A and B worked together.
B's 1 day work = 1/30, so in N days, he can do N * (1/30) of the work, but please note that this does not include the work done by A.
A's 1 day work = 1/20, so in N-10 days, A can complete (N-10)/20 of the work.

Does that help?
Anurag Mairal, Ph.D., MBA
GMAT Expert, Admissions and Career Guidance
Gurome, Inc.
1-800-566-4043 (USA)

Join Our Facebook Groups
GMAT with Gurome
https://www.facebook.com/groups/272466352793633/
Admissions with Gurome
https://www.facebook.com/groups/461459690536574/
Career Advising with Gurome
https://www.facebook.com/groups/360435787349781/

User avatar
Legendary Member
Posts: 582
Joined: Tue Mar 08, 2011 12:48 am
Thanked: 61 times
Followed by:6 members
GMAT Score:740

by force5 » Tue Apr 05, 2011 5:44 am
First, how can we say that A and B together can complete the work in 12 days? (1/20 + 1/30) gives us 1 day work of (A + B) together. But we don't know for how long A and B worked together.
B's 1 day work = 1/30, so in N days, he can do N * (1/30) of the work, but please note that this does not include the work done by A.
A's 1 day work = 1/20, so in N-10 days, A can complete (N-10)/20 of the work.

Does that help?
yes Anurag i understand what you are saying but how did we calculate the combined work that they both did?

I am considering work done to be 1
since both started working together their combined rate is 1/20+1/30= 1/12
which means they can complete the work together in 12 days......
now A leave 10 days before the work could be completed... which means effectively they worked together for 2 days...
in 2 days the amount of work they can do = 1/12*2= 1/6
since A quits B will have to complete the rest of the work..
remaining work is 5/6
B's rate = 1/30
hence time taken = 25 days..
total time 25+2= 27

Problem here is that we cannot calculate A contribution alone because they both started working together... if A worked for n-10 days they we cannot say A contribution is n-10/20 because actually both A and B worked together. Hence we will have to calculate combined rate. Thats why you are getting a smaller value.

User avatar
GMAT Instructor
Posts: 15539
Joined: Tue May 25, 2010 12:04 pm
Location: New York, NY
Thanked: 13060 times
Followed by:1906 members
GMAT Score:790

by GMATGuruNY » Tue Apr 05, 2011 10:16 am
sanju09 wrote:A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?
(A) 12
(B) 16
(C) 18
(D) 26
(E) 27
Plug in job = 60 units.
Rate for A alone = w/t = 60/20 = 3 units per day.
Rate for B alone = w/t = 60/30 = 2 units per day.
Combined rate for A+B together = 3+2 = 5 units per day.
Work completed by B alone in 10 days = r*t = 2*10 = 20 units.
Work to be completed by A+B = 60-20 = 40 units.
Time for A+B to complete 40 units = w/r = 40/5 = 8 days.
Total time = 10+8 = 18 days.

The correct answer is C.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3

Newbie | Next Rank: 10 Posts
Posts: 3
Joined: Mon Apr 04, 2011 6:33 pm

by Mike G » Tue Apr 05, 2011 10:22 am
force5
I used the same logic as you did and got the same answer.It seems essential to calculate combined rate for A and B,work performed by A and B and number of days they worked together.
Also, this method correspondes with that from Manhattan GMAT Word Translation Book.

Anurag,
can you please explain again.

Thanks
Mike

Legendary Member
Posts: 586
Joined: Tue Jan 19, 2010 4:38 am
Thanked: 31 times
Followed by:5 members
GMAT Score:730

by rohu27 » Tue Apr 05, 2011 10:31 am
Solving it using the combined rates approach.
let a and b worked together for x days, B works for 10 more days to finish off the owrk.
so in x days a and b 'together' do x/12 work (as 1 project in 12 days)
remaing work to be done by B in 10 days= 1-x/12=12-x/12
in 10 days B can do 1/3 work,
1/3=12-x/12 on simplification x=8
so the total no of days to complete the given work =8+10=18

force5,Mike,
using the combined rates method too the answer would be same.

User avatar
Legendary Member
Posts: 582
Joined: Tue Mar 08, 2011 12:48 am
Thanked: 61 times
Followed by:6 members
GMAT Score:740

by force5 » Tue Apr 05, 2011 10:35 am
Plug in job = 60 units.
Rate for A alone = w/t = 60/20 = 3 units per day.
Rate for B alone = w/t = 60/30 = 2 units per day.
Combined rate for A+B together = 3+2 = 5 units per day.
Work completed by B alone in 10 days = r*t = 2*10 = 20 units.
Work to be completed by A+B = 60-20 = 40 units.
Time for A+B to complete 40 units = w/r = 40/5 = 8 days.
Total time = 10+8 = 18 days.
Mitch as per me this should be incorrect. it doesn't matter if you take work done as 1 or 60 or 10000. why r u calculating work done by B in 10 days??? how do you know the rest of the work was completed in 10 days??? the question says A quits 10 days before the project was completed( that was when both were working together) obviously now when A quit its going to take longer for B to complete....
Well i don't want to be difficult here for anyone. I described what i felt. Again you guys are the experts if you feel that way i don't want to argue further.....

Thanks guys...

User avatar
GMAT Instructor
Posts: 15539
Joined: Tue May 25, 2010 12:04 pm
Location: New York, NY
Thanked: 13060 times
Followed by:1906 members
GMAT Score:790

by GMATGuruNY » Tue Apr 05, 2011 10:42 am
force5 wrote:Hi anurag... i have a different point of view please correct ...

A and B together can complete the work in 12 days. (1/20+1/30)
now A left 10 days before which means A and B virtually worked for only 2 days.
A total time of 12 days presumes that A and B work together for the entire 12 days.
But since A leaves 10 days early -- leaving B to work alone for much of the project -- the total time will be much more than 12 days.
Thus, we can't say that 12-10 = 2 days is the time that A and B work together.

There is only one known time: for 10 days B works alone.

Thus, the problem could be rephrased:
B works alone on the project for 10 days.
Then A and B work together to finish the project.
What is the total number of days required to complete the project?
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3

Newbie | Next Rank: 10 Posts
Posts: 6
Joined: Tue Apr 05, 2011 9:32 pm

by isanju » Tue Apr 05, 2011 10:08 pm
Let's solve it in reverse order:
B works alone for the last 10 days. So, he completes 1/3 (10/30) part of the complete work.
The remaining 2/3 part of work is completed by A and B together at a rate of (1/30 + 1/20) 1/12 per day. So, A & B together complete the work in 12 days
So, they work together for 8 days (12 * 2/3)
Thus, the total days worked to complete the work in this scenario = 18 (8 + 10)