BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Rate Word Prob

Expert replies
Source: — Problem Solving |

by GmatMathPro » Tue Oct 04, 2011 3:31 pm
Let W=number of workers, C=number of cars to build, and D=number of days to finish the job.

Think about how changing C and W will affect how long it will take to finish the job. Obviously, the more workers you have the better. If you increase the number of people working, the amount of time it takes to finish the job decreases. For example, if you double W, D should be cut in half. If you triple W, D should be multiplied by 1/3. Mathematically, we would say W and D vary inversely. With C and D, though, the more cars to be built, the longer it should take. If you double the number of cars, it should double the number of days. Mathematically, we would say D and C vary directly.

So, if we go from 7 workers to 5 workers, and 7 cars to 5 cars, we've multiplied W by 5/7, which would have the effect of multiplying D by 7/5, the reciprocal factor. However, we've also multiplied the number of cars by 5/7, which has the effect of multiplying D by 5/7. The (7/5)*(5/7) cancel out, so D is unaffected.

If you like formulas, once you establish that W varies inversely with D and C varies directly with D, you could set up the following equation: D=kC/W, where k is some non-zero constant. Now, plug in the initial values of W, C, D to solve for the constant, k. You should get k=7. Now the formula is D=7C/W. PLug in the new values of C and W, C=5 and W=5 to get [spoiler]D=7[/spoiler]
Pete Ackley
GMAT Math Pro
Free Online Tutoring Trial
Join the discussion

by GMATGuruNY » Tue Oct 04, 2011 4:30 pm
gvosough wrote:if 7 workers can build 7 cars in 7 days, then how many days would it take 5 workers to build 5?

A) 1
B) 5
C) 7
D) 25
E) 35

Answer: C

Can s.o. plz explain thank
Let rate per worker = 1 unit per day.
Rate for 7 workers = 7 units per day.
Over 7 days, work produced = 7*7 = 49 units.
Since 49 units = 7 cars, each car = 49/7 = 7 units.
Thus, 5 cars = 5*7 = 35 units.
Rate for 5 workers = 5 units per day.
Time needed = w/r = 35/5 = 7 days.

The correct answer is C.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by edvhou812 » Tue Oct 04, 2011 8:49 pm
If 7 workers can build 7 cars in 7 days, then 7 workers must be able to build 1 car in 1 day. If 7 workers can build a car in one day, then each worker completes 1/7 of the car in that day.

The rate of completion for five workers per day is 1/7+1/7+1/7+1/7+1/7=5/7. So 5 workers complete 5/7 of a car in one day. To answer the question, we create the following equation:

5/7x=5
x=5/1*7/5=35/5=7

So it will take 5 workers, that complete 5/7 of a car per day, 7 days to build 5 cars.
I don't know what to say, really. Three minutes to the biggest battle of our professional lives. You find out life's this game of inches, so is football. Because in either game - life or football - the margin for error is so small. I mean, one half a step too late or too early and you don't quite make it. One half second too slow, too fast and you don't quite catch it. I'll tell you this, in any fight it's the guy whose willing to die whose gonna win that inch. That's football guys, that's all it is. Now, what are you gonna do?
Join the discussion

by sl750 » Tue Oct 04, 2011 10:27 pm
use this ratio

Original # of workers*#of days taken/Work done = New #of workers required *# of days taken/Work done

7*7/7 = 5*W/5 ; W=7
Join the discussion

by Abhishek009 » Wed Oct 05, 2011 4:49 am
gvosough wrote:if 7 workers can build 7 cars in 7 days, then how many days would it take 5 workers to build 5 cars ?

A) 1
B) 5
C) 7
D) 25
E) 35

Answer: C

Can s.o. plz explain thank
If we carefully look at the above problem then we can see that the question given shows us to find the number of days taken to do the work and here efficiency ( Rate of doing work Per unit time ) , remains the same .

Total work done by 7 men in 7 days is - 7 cars


7 * 7 { Total work = No of men * No of days }

Thus 49 men days = 7 cars

So 1 men day = 1/7 man day ( Efficiency )


We also know that


Total work = No of men * No of days * efficiency of the workers

so , 5 = 5 * d * 1/7

So , d * 1/7 = 1

or , d = 7....
Abhishek
Join the discussion

by svd.kumar » Wed Oct 05, 2011 5:53 am
Try This way of thinking

Try to calculate the rate i.e 1 worker per 1 day

7 Workers in 7 Days builds 7 cars
1 Worker in 7 days builds 7/7 = 1 car
1 Worker in 1 day builds 1/7 car (rate)

Which means
Workers * Days * rate (Rate per day per worker) = number of cars (7 * 7 * 1/7 = 7)

So for 5 workers for 5 cars , let d be days
5 * d * 1/7 = 5
d = 7

Answer = 7

Thanks,
SVD