gmatmachoman wrote:50 persons can complete the work in 100 days. In how many days will the work be completed if 10 persons start the work and 10 person join after every 10 days?
in one day, 50 persons complete 1% of the work and a single person completes 1/50 % OR .02% of the work.
in 10 days 10 persons will complete 2% of the work.
in next ten days 20 persons will complete twice this i.e 4% of the work
in next 10, 30 persons will complete 6%
therefore, the total work done in intervals of 10 days becomes :
2+4+6+8+.....
sum of this Arithmetic progression till 9th term 90 = 90
on the 91st day, we have 100 persons working on the job, who complete 2% of the job/day. So, we need 5 more days to have the work completed.
IMO 95 days is the answer.
in ajith's solution, there are few points which are not clear to me :
ajith wrote:till 10th 10 days work worth 4500 man days would be done
We have 110 people to finish remaining 500
who will finish it in 500/110 days
total days = 100 + 50/11
"till 10th 10 days" means 90 days are over. So, while calculating the total days in the end it should be 90+ something.
moreover, on the 91st day we have 100 people not 110, the remaining fraction of work is 500/100.
Please correct me if I'm wrong.