3 machines have a productivity ratio of 1:2:5. all 3 machines are working on a job for 3 hours. at the beginning of the 4th hour, the slowest machine breaks. it is fixed at the beginning at hour 7, and begins working again. the job is done in 9 hours. what was the ratio of the work performed by the fastest machine to the work performed by the slowest?
again, there are no answer options
OA: [spoiler]15:2[/spoiler]
again, there are no answer options
OA: [spoiler]15:2[/spoiler]
















