John can complete a given task in 20 days.

by Vincen » Fri Sep 15, 2017 6:52 pm
John can complete a given task in 20 days. Jane will take only 12 days to complete the same task. John and Jane set out to complete the task by beginning to work together. However, Jane was indisposed 4 days before the work got over. In how many days did the work get over from the time John and Jane started to work on it together?

A) 6
B) 10
C) 8
D) 7.5
E) 3.5

B is the OA.

I've got confused. Can any expert solve it to me?
Source: — Problem Solving |

User avatar
GMAT Instructor
Posts: 15539
Joined: Tue May 25, 2010 12:04 pm
Location: New York, NY
Thanked: 13060 times
Followed by:1906 members
GMAT Score:790

by GMATGuruNY » Fri Sep 15, 2017 7:16 pm
Vincen wrote:John can complete a given task in 20 days. Jane will take only 12 days to complete the same task. John and Jane set out to complete the task by beginning to work together. However, Jane was indisposed 4 days before the work got over. In how many days did the work get over from the time John and Jane started to work on it together?

A) 6
B) 10
C) 8
D) 7.5
E) 3.5
Let the job = the LCM of 20 and 12 = 60 units.

Since John can complete the job in 20 days, John's rate = w/t - 60/20 = 3 units per day.
Since Jane can complete the job in 12 days, Jane's rate = w/t = 60/12 = 5 units per day.

After Jane leaves, John works on his own for 4 days to complete the job.
Work produced by John in the last 4 days = r*t = 3*4 = 12 units.

Of the 60 units that must be produced, John produces the last 12.
Thus, the first 48 units are produced by John and Jane together.
Combined rate for John and Jane = 3+5 = 8 units per day.
Time for John and Jane to produce 48 units = w/r = 48/8 = 6 days.

Total time for the job = (4 days for John alone) + (6 days for John and Jane together) = 10 days.

The correct answer is B.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3

GMAT/MBA Expert

User avatar
GMAT Instructor
Posts: 8086
Joined: Sat Apr 25, 2015 10:56 am
Location: Los Angeles, CA
Thanked: 43 times
Followed by:29 members
Vincen wrote:
Fri Sep 15, 2017 6:52 pm
John can complete a given task in 20 days. Jane will take only 12 days to complete the same task. John and Jane set out to complete the task by beginning to work together. However, Jane was indisposed 4 days before the work got over. In how many days did the work get over from the time John and Jane started to work on it together?

A) 6
B) 10
C) 8
D) 7.5
E) 3.5

B is the OA.

I've got confused. Can any expert solve it to me?
Solution:

We see that John’s rate is 1/20 and Jane’s rate is 1/12.

Letting t = the number of days it takes to get the work completed, we can create the equation:

(1/12) (t - 4) + (1/20) t = 1

Multiplying the equation by 60 we have:

5t - 20 + 3t = 60

8t = 80

t = 10

Alternate Solution:

Since Jane quits 4 days before the job was completed, John worked alone for four days to complete the job. As it takes 20 days for him to complete the whole job, he can complete 1/5 of the job in 4 days. This means that together, they completed 1 - 1/5 = 4/5 of the job.

Since they can complete 1/12 + 1/20 = 8/60 = 2/15 of the job in one day; it will take them (4/5)/(2/15) = 6 days to complete 4/5 of the job. Together with the 4 days John worked alone, it took 6 + 4 = 10 days from the time the two started working together to complete the job.

Answer: B