Can three men and seven women finish a certain piece of work in 15 days?
(1)Two men and four women can finish the work in 10 days
(2)Each of the two women can do twice the work that each of the men can do in a given time

I don't have an OA but detailed explanations would be appreciated.
Source: — Data Sufficiency |

Legendary Member
Posts: 759
Joined: Mon Apr 26, 2010 10:15 am
Thanked: 85 times
Followed by:3 members

by clock60 » Tue Jul 12, 2011 11:31 am
hi knight247
not too sure but i got A here,what is your answer?

Junior | Next Rank: 30 Posts
Posts: 12
Joined: Wed Apr 13, 2011 6:37 am
Thanked: 1 times

by srikanthb.69 » Tue Jul 12, 2011 7:14 pm
Question - (3M +7W)*15 = W ?
1 - Given - (2M + 4W)*10 = W - So even if 1M + 3W sit idle W will be completed in 10days..so answer
is YES and it is Sufficient.

2-Given - w=2M => 3M + 7W = 17M but this dosent say anything about the work..so Not sufficient

Answer is A

Senior | Next Rank: 100 Posts
Posts: 60
Joined: Sat Jul 16, 2011 11:56 pm
Location: hyderabad
Thanked: 2 times
Followed by:1 members

by naveen451 » Sat Aug 06, 2011 6:08 am
IMO C

Legendary Member
Posts: 2789
Joined: Tue Jul 26, 2011 12:19 am
Location: Chennai, India
Thanked: 206 times
Followed by:43 members
GMAT Score:640

by GmatKiss » Sat Aug 06, 2011 6:39 am
IMO: A

User avatar
Legendary Member
Posts: 1077
Joined: Mon Dec 13, 2010 1:44 am
Thanked: 118 times
Followed by:33 members
GMAT Score:710

by bblast » Sat Aug 06, 2011 6:46 am
to add on to Srikanth's soln :

(2M + 4W) = 10 days

(1M + 2W) = 20 days

thus,
(3M + 6W) = 20/3 days = 6.6 days



question asks (3M + 7W)- thus we have a women extra and we already can complete the work in 6.6 days.

A
Cheers !!

Quant 47-Striving for 50
Verbal 34-Striving for 40

My gmat journey :
https://www.beatthegmat.com/710-bblast-s ... 90735.html
My take on the GMAT RC :
https://www.beatthegmat.com/ways-to-bbla ... 90808.html
How to prepare before your MBA:
https://www.youtube.com/watch?v=upz46D7 ... TWBZF14TKW_

User avatar
Master | Next Rank: 500 Posts
Posts: 312
Joined: Tue Aug 02, 2011 3:16 pm
Location: New York City
Thanked: 130 times
Followed by:33 members
GMAT Score:780

by gmatboost » Sun Aug 07, 2011 10:50 pm
This is a bad question for at least two reasons:

1. Statement 1 is a bit strange. As others have pointed out, if we know 2 men and 4 women can do a job in 10 days, of course more people with more time will be able to the job.

2. The unstated assumption (for Statement 1 at least) that all men work at the same rate and all women work at the same rate is a little ridiculous. Maybe the addition of more men will mean men get in the way and stop work from being done? Maybe they will go off and watch TV...
Greg Michnikov, Founder of GMAT Boost

GMAT Boost offers 250+ challenging GMAT Math practice questions, each with a thorough video explanation, and 100+ GMAT Math video tips, each 90 seconds or less.
It's a total of 20+ hours of expert instruction for an introductory price of just $10.
View sample questions and tips without signing up, or sign up now for full access.


Also, check out the most useful GMAT Math blog on the internet here.