claudayst wrote:Machine A can complete a certain job in x hours. Machine B can complete the same job in y hours. If A and B work together at their respective rates to complete the job, which of the following represents the fraction of the job that B will not have to complete?
(x - y)/(x + y)
x/(y - x)
(x + y)/xy
y/(x - y)
y/(x + y)
In other words:
What fraction of the job will be completed by A?
The TIME RATIO for A and B = x:y.
Since time and rate are reciprocals, the RATE RATIO for A and B = y : x.
Implication of the rate ratio:
Of every y+x units produced each hour, A produces y units and B produces x units.
Thus, (work produced by A each hour)/(total work produced each hour) = y/(y+x).
The correct answer is
E.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.
As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.
For more information, please email me (Mitch Hunt) at
[email protected].
Student Review #1
Student Review #2
Student Review #3