A completes the job in 30 days, B in 20 days and C demolishes the construction in 60 days, each person working alone. When will the construction be complete if they work on alternate day starting with A, then B and then C??
In the first 3 days, they complete (1/30 + 1/20 - 1/60) = 4/60 = 1/15 of the complete work.neya wrote:A completes the job in 30 days, B in 20 days and C demolishes the construction in 60 days, each person working alone. When will the construction be complete if they work on alternate day starting with A, then B and then C?
Hence, in the first 42 days, they will complete (42/3)*(4/60) = 14/15 of the complete work.
Thus, work left after 42nd day = 1/15 of the complete work.
In 43rd day, A will finish 1/30 of the work.
And B will complete the rest of the (1/15 - 1/30) = 1/30 of the work in 20/30 = 2/3 day.
Hence, total time required = (43 + 2/3) days.












