A contract is to be completed in 46 days and 117 men were set to work, each working 8 hrs a day. After 33 days 4/7 of the work is completed. How many additional men may be employed so that the work may be completed in time, each men now working 9 hrs a day?
a.46
b.57
c.64
d.75
e.81