BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATBootcamp Starts Sep 21
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE BOOTCAMP

Live Online Bootcamp Class with Top GMAT Expert Chris Peckover

Sep 21 to Oct 9, 2026

Schedule
Mon to Fri · 7:00 to 10:00 PM ET
Included
Live classes + 6 months of TTP OnDemand
  • Boost your GMAT score in less than one month in a live online class
  • 6 months access to TTP OnDemand video courses included
View bootcamp & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

One machine, working at a constant rate, can fill a certain production order in 8 hours. How long would it take four...

Expert replies
by AAPL » Thu Jul 09, 2020 3:23 am

Timer

00:00

Answers

A

B

C

D

E

Stats

Difficulty

Veritas Prep

One machine, working at a constant rate, can fill a certain production order in 8 hours. How long would it take four identical machines, working at the same constant rate, to fill the order?

A. 2 hours
B. 4 hours
C. 8 hours
D. 16 hours
E. 32 hours

OA A
Join the discussion
Source: — Problem Solving |

AAPL wrote:
Thu Jul 09, 2020 3:23 am
Veritas Prep

One machine, working at a constant rate, can fill a certain production order in 8 hours. How long would it take four identical machines, working at the same constant rate, to fill the order?

A. 2 hours
B. 4 hours
C. 8 hours
D. 16 hours
E. 32 hours

OA A
One machine can fill a certain production order in 8 hours; thus 4 machines can fill a certain production order in 8/4 = 2 hours.

Correct answer: A

Hope this helps!

-Jay
_________________
Manhattan Review GMAT Prep

Locations: Manhattan TOEFL | IELTS Practice Questions | GMAT Practice Test | ACT Info | and many more...

Schedule your free consultation with an experienced GMAT Prep Advisor! Click here.
Join the discussion

Given that rate of work done is constant
If 1 machine can complete 1 order in 8 hours; it will complete x order in 1 hour
x=1/8

If 1 machine completes 1/8 order in 1 hour, then 4 machines will complete 1/8 * 4 in 1 hour
=> 4 machines will complete 1/2 in 1 hour

If it takes 1 hour for 4 machines to complete 1/2 of production order; it will take y hours for 4 machines to complete 1/1 of the order

$$\frac{1}{2}y=1$$
$$y=1\cdot\frac{2}{1}$$
$$y=2\ hours$$

$$Answer\ =\ A$$