If 12 men and 16 women can do a piece of work in 5 days and 13 men and 24 women can do it in 4 days, how long will 7 men and 10 women take to do it?
(A) 4.2 days
(B) 6.8 days
(C) 8.3 days
(D) 9.8 days
(E) 10.2 days
Answer: C
Source: GMAT Prep
(A) 4.2 days
(B) 6.8 days
(C) 8.3 days
(D) 9.8 days
(E) 10.2 days
Answer: C