I 'm not understand the explaination answer. plz help and explain in the easier way.
1. 15 Java programmers, working in a constant pace, finish a web page in 3 days. If after one day, 9 programmers quit, how many more days are needed to finish the remainder of the job?
(a) 5.
(b) 2.
(c) 8.
(d) 4.
(e) 6.
The best answer is A.
The total working days for finishing a web page are (15 x 3) 45. If after one day 9 programmers quit, only 15 working days are done and the rest of the programmers (6)
Need to finish (45 – 15) 30 days of work. It will take them 5 more days.
1. 15 Java programmers, working in a constant pace, finish a web page in 3 days. If after one day, 9 programmers quit, how many more days are needed to finish the remainder of the job?
(a) 5.
(b) 2.
(c) 8.
(d) 4.
(e) 6.
The best answer is A.
The total working days for finishing a web page are (15 x 3) 45. If after one day 9 programmers quit, only 15 working days are done and the rest of the programmers (6)
Need to finish (45 – 15) 30 days of work. It will take them 5 more days.