BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
Vote for Target Test Prep, Newsweek Readers’ Choice Awards 2026
NEWSWEEK READERS’ CHOICE 2026

BIG NEWS! Target Test Prep has been nominated, and they’d love your vote!

TTP has worked incredibly hard to build the best test prep experience possible, and winning Newsweek’s 2026 Readers’ Choice Award for Best Test Prep would mean a lot to them. If TTP has helped you, they’d be incredibly grateful for your vote. You can vote once each day through September 9.

Vote for TTP
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Plz explain this Work problem

Expert replies
by prameko » Sat Apr 12, 2008 12:04 pm
I 'm not understand the explaination answer. plz help and explain in the easier way.

1. 15 Java programmers, working in a constant pace, finish a web page in 3 days. If after one day, 9 programmers quit, how many more days are needed to finish the remainder of the job?

(a) 5.
(b) 2.
(c) 8.
(d) 4.
(e) 6.

The best answer is A.
The total working days for finishing a web page are (15 x 3) 45. If after one day 9 programmers quit, only 15 working days are done and the rest of the programmers (6)
Need to finish (45 – 15) 30 days of work. It will take them 5 more days.
Join the discussion
Source: — Problem Solving |

Re: Plz explain this Work problem

by Musiq » Sat Apr 12, 2008 1:27 pm
prameko wrote:I 'm not understand the explaination answer. plz help and explain in the easier way.

1. 15 Java programmers, working in a constant pace, finish a web page in 3 days. If after one day, 9 programmers quit, how many more days are needed to finish the remainder of the job?

(a) 5.
(b) 2.
(c) 8.
(d) 4.
(e) 6.
Hi Prameko,

There are many ways to approach this question, but in my opinion, the following is a universal approach in that it can be expanded to accomodate any subtlety that GMAT test-makers impose on us. So, in reality it works in every proportionailty problem AND more importantly we understand what we are doing.

The assumption of every such question is that all people work exactly at the same rate (unless otherwise specified)

15 Programmers------------ 1 job -------------------- 3 days.
Therefore,
1 programmer----------------1 job ------------------- (15) (3) = 45 days.

Also,
15 programmers ------------1/3rd job -----------------1 day.

{ ^^This is a very important step in the problem, coz now you can answer any question that can be posed, since you have converted everything into rates based on 1 day or 1 person}

{The Condition: 9 programmers leave after 1 day. But, the 15 programmers finished 1 day's work together. This is 1/3rd of the work. This leaves 2/3rds of the work to be finished.}

There are only 6 programmers left to finish the webpage. What is the rate of work of 6 programmers on this kind of a job?

1 programmer-----------------1 job------------------------ 45 days.
Therefore,
6 programmers--------------- 1 job----------------------- 45/6 days (since work gets shared and gets done faster).

But we need only 2/3rd of the work to get done.

6 programmers---------------1 job---------------------45/6 days
6 programmers--------------2/3rd job----------------- ??????

Multiply 45/6 with 2/3rds to get the answer as 5 days more .qa = A.

The last step is a standard proportionality set-up. If you need any help with that, please let me know.
For love, not money.
Join the discussion

Thank you Musiq

by prameko » Sat Apr 12, 2008 8:57 pm
Thank You Musiq for your easier explaination.
I'm understand it better now . I always have problem about this kind of work problems. I take so long time to solve it.

Actually, I just had GMAT test last week and I was so upset about it. I could not finish it on time (many questions left) both math and verbal. I plan to retake next month. Can I have ur suggestion to improve about 100? Moreover, I may have many GMAT to ask you later.
Join the discussion

Re: Thank you Musiq

by Musiq » Sat Apr 12, 2008 9:05 pm
prameko wrote: Actually, I just had GMAT test last week and I was so upset about it. I could not finish it on time (many questions left) both math and verbal. I plan to retake next month. Can I have ur suggestion to improve about 100? Moreover, I may have many GMAT to ask you later.
Please feel free to ask any questions. As far as my knowledge extends, I will help you.

Good luck when you retake the exam. Dont be upset that you have to retake the exam.

GMAC has research that shows 23% of all test-takers repeat the exam. Thats 1 in 4 people.

My point is that its not you, its probably the GMAT itself. Luckily we know that the GMAT has a set testing phiolosophy. Try to capture that in your preparation.

That will really help. And of course, please finish the test. Thats really important. Unfinished tests result in huge score losses.
For love, not money.
Join the discussion

work problem again

by prameko » Sun Apr 13, 2008 10:48 pm
Can u explain another one.

2. Two carpenters, working in the same pace, can build 2 desks in two hours and a half. How many desks can 4 carpenters build in 4 hours?

(a) 2.4.
(b) 3.6.
(c) 4.2.
(d) 5.5.
(e) 6.4

The best answer is E.
2 carpenters build 2 desks in 2.5 hours ---> 4 carpenters build 4 desks in 2.5 hours ----> In 4 hours there are (4/2.5 = 1.6) time units. And (4 x 1.6) is 6.4 desks.
Join the discussion

Re: work problem again

by gabriel » Mon Apr 14, 2008 3:13 am
prameko wrote:Can u explain another one.

2. Two carpenters, working in the same pace, can build 2 desks in two hours and a half. How many desks can 4 carpenters build in 4 hours?

(a) 2.4.
(b) 3.6.
(c) 4.2.
(d) 5.5.
(e) 6.4

The best answer is E.
2 carpenters build 2 desks in 2.5 hours ---> 4 carpenters build 4 desks in 2.5 hours ----> In 4 hours there are (4/2.5 = 1.6) time units. And (4 x 1.6) is 6.4 desks.

Hi Prameko,

Welcome to BTG. Please do start a new question on a new thread. This will help everyone keep track of the question better.

Regards

@Musiq.. nice explanations btw
Join the discussion

by gmat765 » Thu Apr 17, 2008 7:53 pm
thanks, musiq. your explanation is very clear
Join the discussion

hi

by Jeff@TargetTestPrep » Fri Jan 05, 2018 7:22 am
15 Java programmers, working in a constant pace, finish a web page in 3 days. If after one day, 9 programmers quit, how many more days are needed to finish the remainder of the job?

(a) 5
(b) 2
(c) 8
(d) 4
(e) 6
We know that the daily rate of 15 workers is 1/3 of the job. To find the daily rate of 6 workers, then, we can set up the following proportion:

15/(1/3) = 6/x

45 = 6/x

45x = 6

x = 6/45 = 2/15 (This is the daily rate of 6 workers.)

Since after 1 day of work 1/3 of the job is completed, the 6 workers now have to complete the remaining 2/3 of the job at the rate of 2/15 of the job per day.

We use the formula work = rate x time. We let x = the time it will take the 6 workers to finish 2/3 of the job.

2/3 = (2/15)(x)

30/6 = x

x = 5

Answer: A