BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Time and work problem

Expert replies
by hemant_rajput » Sat Jan 26, 2013 9:47 pm
Q22 . It takes 6 days for 3 women and 2 men working together to complete a work. 3 men would do the same work 5 days sooner than 9 women. How many times does the output of a man exceed that of a woman ?

a. 3
b. 4
c. 5
d. 6
e. 7
I'm no expert, just trying to work on my skills. If I've made any mistakes please bear with me.
Join the discussion
Source: — Problem Solving |

by jkaustubh » Sat Jan 26, 2013 10:14 pm
x: days 9 women doing the job --> 1 woman works W=1/9x per day
x-5: days 3 men doing the job --> 1 man works M=1/[3*(x-5)] per day

The answer to the question is: M/W

And, how much is x?

As per first data:

2*M+3*W=1/6
You can solve x, and obtain 2 values, 10 and 1 (1 is impossible because that would imply that the 3 men take -4 days), so x=10. So M/W=6 times
Replying a query takes patience and time. The least a person can do is to thank the reply.
Join the discussion

by GMATinsight » Sun Jul 15, 2018 10:15 pm
Please find attached the solution
Image
"GMATinsight"Bhoopendra Singh & Sushma Jha
Most Comprehensive and Affordable Video Course 2000+ CONCEPT Videos and Video Solutions
Whatsapp/Mobile: +91-9999687183 l [email protected]
Contact for One-on-One FREE ONLINE DEMO Class Call/e-mail
Most Efficient and affordable One-On-One Private tutoring fee - US$40-50 per hour
Join the discussion

by GMATGuruNY » Mon Jul 16, 2018 2:24 am
hemant_rajput wrote:Q22 . It takes 6 days for 3 women and 2 men working together to complete a work. 3 men would do the same work 5 days sooner than 9 women. How many times does the output of a man exceed that of a woman ?

a. 3
b. 4
c. 5
d. 6
e. 7
We can PLUG IN THE ANSWERS, which represent how many times a man's output exceeds that of a woman.
When the correct answer is plugged in, 3 men will take 5 fewer days to complete the job than 9 women.

B: 4
Let the rate for each woman = 1 unit per day and the rate for each man = 4 units per day.
Since it takes 6 days for 3 women and 2 men to complete the job, the job = (rate for 3 women and 2 men)(6 days) = (3*1 + 2*4)(6) = 66 units.
Time for 9 women to complete the job = (work)/(rate for 9 women) = 66/(9*1) = 22/3 ≈ 7 days.
Time for 3 men to complete the job = (work)/(rate for 3 men) = 66/(3*4) = 66/12 = 11/2 ≈ 5 days.
Doesn't work:
Here, 3 men take only about 2 fewer days than 9 women.
Eliminate B.
For 3 men to take 5 fewer days, the rate for each man must INCREASE.
Eliminate A.

D: 6
Let the rate for each woman = 1 unit per day and the rate for each man = 6 units per day.
Since it takes 6 days for 3 women and 2 men to complete the job, the job = (rate for 3 women and 2 men)(6 days) = (3*1 + 2*6)(6) = 90 units.
Time for 9 women to complete the job = (work)/(rate for 9 women) = 90/(9*1) = 90/9 = 10 days.
Time for 3 men to complete the job = (work)/(rate for 3 men) = 90/(3*6) = 90/18 = 5 days.
Success!
Here, 3 men take 5 fewer days than 9 women.

The correct answer is D.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by swerve » Mon Jul 16, 2018 9:37 am
First set: 3/w+2/m=1/6

Second set: 3/m = 1/x and 9/w=1/(x+5)

--> 1/m = 1/3x and 1/w = 1/9(x+5)

Enter in the first equation and solve for x

1/(3x+15) + 2/3x = 1/6

Simplify --> x^2-x-20=0

Solve for x: x=(1 +- (1+80)^,5)/2= (1+- 9)/2.

x can only be positive ---> x= 5.

Enter in the second set ---> 3/m=1/5 and 9/w=1/10 --> 3/2m=9/w --> m/w=1/6.

Regards!
Join the discussion

by Scott@TargetTestPrep » Thu Jul 19, 2018 11:40 am
hemant_rajput wrote:Q22 . It takes 6 days for 3 women and 2 men working together to complete a work. 3 men would do the same work 5 days sooner than 9 women. How many times does the output of a man exceed that of a woman ?

a. 3
b. 4
c. 5
d. 6
e. 7
We can let the number of days for 1 man to finish the work = m and that for 1 woman = w. Thus, the rate of 1 man = 1/m and the rate of 1 woman = 1/w.

Since it takes 6 days for 3 women and 2 men working together to complete the work, we have:

6(3/w + 2/m) = 1

Since 3 men would do the same work 5 days sooner than 9 women, we have:

1/(3/m) + 5 = 1/(9/w)

m/3 + 5 = w/9

Multiplying the above by 9, we have:

3m + 45 = w

Substituting this into 6(3/w + 2/m) = 1, we have:

6(3/(3m + 45) + 2/m) = 1

6(1/(m + 15) + 2/m) = 1

Multiplying the above by m(m + 15), we have:

6m + 12(m + 15) = m(m + 15)

6m + 12m + 180 = m^2 + 15m

m^2 - 3m - 180 = 0

(m - 15)(m + 12) = 0

m = 15 or m = -12

Since m can't be negative, m = 15. So w = 3(15) + 45 = 90. We see that it takes a man 15 days to complete the work but 90 days for a woman to complete the same work. So a man's output is 6 times the output of a woman.

Answer: D

Scott Woodbury-Stewart
Founder and CEO
[email protected]

Image

See why Target Test Prep is rated 5 out of 5 stars on BEAT the GMAT. Read our reviews

ImageImage
Join the discussion

Time and work problem

by Mo2men » Fri Jul 20, 2018 3:55 pm
GMATinsight wrote:Please find attached the solution
Image
Dear GMAtInsight,

I saw you many times use the formula (MT)/W =constant but M is manpower. However, when you tried to solve the problem you used (3w+2m) *6/1 . Now, I'm confused why you said is 3w + 2m represents a rate but as manpower should be a number like 5 people not rate. ?

I feel something not right about manpower? what is the unite of manpower? is it (unit produced/unite of time) ?

Also, how are all equal to constant? What does constant here mean? Can you elaborate more please?

Thanks in advance