\(A\) can complete a piece of work in \(x\) days and \(B\) can do the same piece of work in \(y\) days. If \(B\) starts working a day after \(A\) and then they work together, in how many days can they complete the work?

1. \(x = 100\)
2. \(x: y = 2: 1\)

Answer: C