pj94z wrote:bob paints house in 8 hrs by himself.
joe paints house in 6 hrs by himself.
how long will it take to paint the house together ?
Let's try this problem. Neo is right, but he skipped some steps and I can understand if you are confused.
First you want to convert the above into RATES
Bob takes 8 hours to finish 1 house which converts mathematically as 1 house per 8 hours or 1/8. That means Joe rate is 1/6.
Their combined rates is 1/8 + 1/6 = 14/48 = 7/24
The formula of Rate*Time = Work
We know what Rate and Work are - Work is 100% of 1 house and rate is 7/24
7/24*T = 1
T = 24/7
Pretty simple.