If x persons take y days to complete z similar jobs, how long does it take y persons to complete 1 such job?
A. z
B. x
C. x/y
D. z/x
E. x/z
The OA is E.
x person - z jobs in y days
x person - 1 job in y/z days
1 person - 1 job in y/zx days
y person - 1 job in y^2/zx
Am I missing something ?? Isn't the right way to do it ?? Can anyone assist me, please? Thanks in advance!