BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Work Rate DS Problem

Expert replies
by Bens4vcobra » Mon Jun 20, 2011 4:14 pm
To fill an order on schedule, a manufacturer had to produce 1000 tools per day for N days, what is the value of N?

1) Because of production problems, the manufacturer only produced 600 tools for the first 5 days
2) Because of production problems, the manufacturer had to produce 1500 tools per day for each of the last 4 days to meet the schedule
"It takes no ability to give effort. Toughness is not God-given; it's a choice. The discipline to execute is a habit." - Nick Saban
Join the discussion
Source: — Data Sufficiency |

by ChrisK » Mon Jun 20, 2011 10:01 pm
Hi, IMHO:

This is a work rate problem. Upfront, we have:

Rate = 1000/day
Time = N days
Job = 1000N

Therefore, in order to get the value of N, we need to know the value of the job.

Statement #1 - This tells us that the manufacturer has produced only 600 tools over the first five days, but tells us nothing about how many more days the manufacturer will be producing tools.

State#2 - This tells us that over the last 4 days, the manufacturer produced 1500 tools/day (6,000 total) but does not tell us how many days of production problems the manufacturer had.

Neither of the statements individually tell us enough to answer the question.

Let's look at them together.

Statement #1 tells us that we have 600 tools after 5 days. Statement #2 tells us that the job is done once 6,000 more tools are produced. Taken together, this tells us that the job is for 6,600 tools total.

Going back to the original question;
Job = rate X time
6,600 = 1,000 X N
N = 6.6 days

Therefore, the answer is [spoiler]'C'[/spoiler]
Join the discussion

by Frankenstein » Mon Jun 20, 2011 10:04 pm
Bens4vcobra wrote: 1) Because of production problems, the manufacturer only produced 600 tools for the first 5 days
Hi,
Can you check statement(1) again. Is it 600tools per day for the first 5 days? Please check for errors while posting the question.
Cheers!

Things are not what they appear to be... nor are they otherwise
Join the discussion

by Geva@EconomistGMAT » Mon Jun 20, 2011 10:13 pm
Bens4vcobra wrote:To fill an order on schedule, a manufacturer had to produce 1000 tools per day for N days, what is the value of N?

1) Because of production problems, the manufacturer only produced 600 tools for the first 5 days
2) Because of production problems, the manufacturer had to produce 1500 tools per day for each of the last 4 days to meet the schedule
Meh. Obviously neither of the statements is sufficient on its own. I guess they want you to think that the combination is sufficient (600+ 4*1500 = 6600, so N=7). The problem is that the statements are phrased as "the first 5 days" and "the last 4 days" - not "the first 5 days" and the "NEXT four days". Between the first 5 and the last 4, you can sneak in a whole YEAR of working at exactly 1000 tools per day - there's no requirement that the last 4 come immediately after the first 5. Answer should be E.

EDIT: 600 for the first 5 days altogether, not 600 per day. Doesn't matter.
Geva
Senior Instructor
Master GMAT
1-888-780-GMAT
https://www.mastergmat.com
Join the discussion

by worldpeace93 » Mon Jun 20, 2011 10:34 pm
Answer should be E,as both statements combined or alone don't metion the total no of working days.
Join the discussion

by bubbliiiiiiii » Tue Jun 21, 2011 12:28 am
Thanks Geva@MasterGMAT sir for your insights. :)

Even I picked C and then later understood why E and not C.
Regards,

Pranay
Join the discussion

by ChrisK » Tue Jun 21, 2011 2:53 am
Thanks guys, that was a critical oversight on my part.

Sorry Bens.

Chris
Join the discussion

by Bens4vcobra » Tue Jun 21, 2011 6:29 am
ChrisK wrote:Thanks guys, that was a critical oversight on my part.

Sorry Bens.

Chris
No problem I did exactly what you did! I assumed the total days were 9 and that the order was filled on schedule. I fell for the trap.
Last edited by Bens4vcobra on Tue Jun 21, 2011 6:31 am, edited 1 time in total.
"It takes no ability to give effort. Toughness is not God-given; it's a choice. The discipline to execute is a habit." - Nick Saban
Join the discussion

by Bens4vcobra » Tue Jun 21, 2011 6:30 am
Frankenstein wrote:
Bens4vcobra wrote: 1) Because of production problems, the manufacturer only produced 600 tools for the first 5 days
Hi,
Can you check statement(1) again. Is it 600tools per day for the first 5 days? Please check for errors while posting the question.
Pretty sure I typed the question correctly.
"It takes no ability to give effort. Toughness is not God-given; it's a choice. The discipline to execute is a habit." - Nick Saban
Join the discussion

by Sanjay2706 » Mon Jun 27, 2011 2:04 am
Answer is E, as it is not clear whether there were only 9 days.
The first 5 days and last 4 days does not mean that there were only 9 days.
Tricky one.
Join the discussion