claudayst wrote:What is the formula or rather the rationale for computing a combined rate but just for a portion of the work, for example two machines working together for a certain amount of time and then one of the machine stops while the other continues. The way around as well: one machine start working and then another one joins. Many thx in advance!
I think these examples should serve as an answer to your question:
Example 1--
A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in :
Explanation:
(A + B)'s 1 day's work = ( 1/15 + 1/10 ) = 1/6
Work done by A and B in 2 days = ( 1/6 x 2 ) = 1/3
Remaining work = ( 1 - 1/3 ) = 2/3
Now, 1/15 work is done by A in 1 day.
Therefore 2/3 work will be done by A in ( 15 x 2/3 ) = 10 days.
Hence, the total time taken = (10 + 2) = 12 days.
Example 2--
X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?
Explanation:
Work done by X in 4 days = (1/20 x 4 ) = 1/5
Remaining work = (1 - 1/5) = 4/5
(X + Y)'s 1 day's work = (1/20 + 1/12) = 8/60 = 2/15
Now, 2/15 work is done by X and Y in 1 day.
So, 4/5 work will be done by X and Y in 15/2 x 4/5 = 6 days.
Hence, total time taken = (6 + 4) days = 10 days.
Polish your skills till you achieve perfection.