Six machines working at the same rate constant rate complete a job in 12 days.
How many additional machines working at same rate will be needed to complete
the job in 8 days?
a. 2
b. 3
c. 4
d. 6
e. 8

Ans:3
Source: — Problem Solving |

User avatar
Master | Next Rank: 500 Posts
Posts: 436
Joined: Tue Feb 08, 2011 3:07 am
Thanked: 72 times
Followed by:6 members

by manpsingh87 » Sat May 14, 2011 11:56 pm
agni_h1 wrote:Six machines working at the same rate constant rate complete a job in 12 days.
How many additional machines working at same rate will be needed to complete
the job in 8 days?
a. 2
b. 3
c. 4
d. 6
e. 8

Ans:3
machine required would be 6*12/8=9; hence additional machines required= 9-6=3;