printers X, Y, and Z

Expert replies
by Ankitaverma » Wed Dec 04, 2013 10:39 am
Working alone, printers X, Y, and Z can do a certain printing job, consisting of a large number of pages, in 12, 15, and 18 hours, respectively. What is the ratio of the time it takes printer X to do the job, working alone at its rate, to the time it takes printers Y and Z to do the job, working together at their individual rates?

a 4/11
b 1/2
c 15/22
d 22/15
e 11/4

Q/A-d why not c
Join the discussion
Source: — Problem Solving |

by Brent@GMATPrepNow » Wed Dec 04, 2013 10:41 am
Ankitaverma wrote:Working alone, printers X, Y, and Z can do a certain printing job, consisting of a large number of pages, in 12, 15, and 18 hours, respectively. What is the ratio of the time it takes printer X to do the job, working alone at its rate, to the time it takes printers Y and Z to do the job, working together at their individual rates?

a 4/11
b 1/2
c 15/22
d 22/15
e 11/4
For work questions, there are two useful rules:
Rule #1: If a person can complete an entire job in k hours, then in one hour, the person can complete 1/k of the job
Example: If it takes Sue 5 hours to complete a job, then in one hour, she can complete 1/5 of the job. In other words, her work rate is 1/5 of the job per hour

Rule #2: If a person completes a/b of the job in one hour, then it will take b/a hours to complete the entire job
Example: If Sam can complete 1/8 of the job in one hour, then it will take him 8/1 hours to complete the job.
Likewise, if Joe can complete 2/3 of the job in one hour, then it will take him 3/2 hours to complete the job.

Let's use these rules to solve the question. . . .

Printer Y takes 15 hours to complete a job. So, by rule #1, printer Y's rate is 1/15 of the job per hour
Printer Z takes 18 hours to complete a job. So, by rule #1, printer Z's rate is 1/18 of the job per hour
So, their combined rate per hour = 1/15 + 1/18
= 6/90 + 5/90
= 11/90
So, working together, printers Y and Z can complete the 11/90 of the job in one hour.
When we apply rule #2, we can conclude that, working together, printers Y and Z will complete the entire job in 90/11 hours.


What is the ratio of the time it takes printer X to do the job, working at its rate, to time it takes printers y and z to do the job?
So, (time for X to complete)/ (time for Y & Z to complete) = 12/(90/11)
= (12)(11/90)
= [spoiler]22/15[/spoiler]
= D

Cheers,
Brent
Brent Hanneson - Creator of GMATPrepNow.com
Image
Join the discussion

by [email protected] » Wed Dec 04, 2013 2:50 pm
Hi Ankitaverma,

This question is perfect for the "work formula." While there are 3 machines, only 2 of them are actually working together.

Work Formula = (AxB)/(A+B)

X = 12 hours to do a job
Y = 15 hours to do a job
Z = 18 hours to do a job

Together, Y and Z takes....

(15x18)/(15+18) hours to do the job.

270/33 = 90/11 hours

The ratio of X to (YandZ) = 12/(90/11) = 12(11)/90 = 132/90 = 22/15

Final Answer: D

GMAT assassins aren't born, they're made,
Rich
Contact Rich at [email protected]
Image
Join the discussion

by Mathsbuddy » Thu Dec 05, 2013 3:05 am
Print rate = no. of jobs/time

Rate X = 1/12
Rate Y = 1/15
Rate Z = 1/18

Rate of (Y + Z) = 1/15 + 1/18 = 11/90
So time for (Y + Z) = 90/11

Time for X/Time for (Y + Z) = 12/(90/11) = 12 * 11/90 = 22/15
ANSWER D