BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

20 workmen can make 35 widgets in 5 days.

Expert replies
by Vincen » Fri Sep 22, 2017 11:00 am
20 workmen can make 35 widgets in 5 days. How many workmen are needed to make 105 widgets in 5 days?

(A) 7
(B) 20
(C) 25
(D) 30
(E) 60

The OA is E.

What are the calculations to solve this PS question? Experts I need help here. Thanks.
Join the discussion
Source: — Problem Solving |

by Brent@GMATPrepNow » Fri Sep 22, 2017 1:08 pm
Vincen wrote:20 workmen can make 35 widgets in 5 days. How many workmen are needed to make 105 widgets in 5 days?

(A) 7
(B) 20
(C) 25
(D) 30
(E) 60
Given: 20 workmen can make 35 widgets in 5 days.

If we DOUBLE the number of workmen, then those workmen will make TWICE as many widgets in 5 days.
So, 40 workmen can make 75 widgets in 5 days.

Likewise, If we TRIPLE the number of workmen, then those workmen will make THREE TIMES as many widgets in 5 days.
So, 60 workmen can make 105 widgets in 5 days.

Answer: E

Cheers,
Brent
Brent Hanneson - Creator of GMATPrepNow.com
Image
Join the discussion

by [email protected] » Sat Sep 23, 2017 9:47 am
Hi Vincen,

When dealing with these types of 'work' questions, it can be helpful to think in terms of the total amount of work that needs to be done to complete the given task. We're told that it takes 20 workmen 5 days to complete the task. That's...

(20 men)(5 days each) = 100 work-days of effort to create 35 widgets.

Thus, there are a number of different ways to complete that work:
1 worker can work for 100 days
2 workers can work for 50 days each
4 workers can work for 25 days each
Etc.

The question asks us to create 105 widgets, which is 3 times the 35 in the above calculation. Those 105 widgets would take 3(100) = 300 work-days of effort. If we have to complete the job in 5 days, then we can set up the following equation:

(X men)(5 days each) = 300 work-days

X = 60 men

Final Answer: E

GMAT assassins aren't born, they're made,
Rich
Contact Rich at [email protected]
Image
Join the discussion

hi

by Jeff@TargetTestPrep » Mon Dec 18, 2017 10:53 am
Vincen wrote:20 workmen can make 35 widgets in 5 days. How many workmen are needed to make 105 widgets in 5 days?

(A) 7
(B) 20
(C) 25
(D) 30
(E) 60
We are given that the rate of 20 workmen is 35/5 = 7 widgets per day. We need to determine how many workmen are needed for a rate of 105/5 = 21 widgets per day. We can let x = the number of workman and create the following proportion:

20/7 = x/21

(20)(21) = 7x

(20)(3) = x

60 = x

E

Jeffrey Miller
Head of GMAT Instruction
[email protected]

Image