The amount of time that three people worked on a certain project was in the ratio of 2 : 3 : 5. If the project took 110

Expert replies
by Vincen » Mon May 18, 2020 6:49 am

Timer

00:00

Answers

A

B

C

D

E

Stats

Difficulty

The amount of time that three people worked on a certain project was in the ratio of 2 : 3 : 5. If the project took 110 hours, what is the difference between the number of hours worked by the person who worked for the longest time and the person who worked for the shortest time?

(A) 22
(B) 33
(C) 44
(D) 55
(E) 66

[spoiler]OA=B[/spoiler]

Source: Manhattan GMAT
Join the discussion
Source: — Problem Solving |

Given that => Project took 110 hours
The ratio of work for the 3 people = 2 : 3 : 5
Let 3 people = x, y, z
The ratio of x : y : z = 2 : 3 : 5
Sum of ratio = 2 + 3 + 5 = 10

x worked for => 110 * 2/10 hours
= 22 hours
y worked for => 110 * 3/10 hours
= 33 hours
z worked for 110 * 5/10 hours
= 55 hours

x worked for the shortest time
z worked for the longest time
The difference between their working hours
=> z - x hour
= 55 - 22 = 33 hours

Answer = B