BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

A, B and C working alone can complete a work in 24

Expert replies
by vinni.k » Sat Sep 07, 2013 7:48 am
A, B and C working alone can complete a work in 24, 32, and 48 days respectively. "A" started the work and "B" joined him after 4 days and "C" joined them after 4 more days. If they were paid $10,800 for the work done, how much did "A" get ?

(A) 2800
(B) 3600
(C) 5400
(D) 6400
(E) 7600

OA is D

Thanks & Regards
Vinni
Join the discussion
Source: — Problem Solving |

by Anindya Madhudor » Sat Sep 07, 2013 8:32 am
In 4 days, A completes 4/24 part of the whole work. Remaining work is 20/24 after 4 days.
When B joins after 4 days, A and B together do (1/24 + 1/32)*4 = 7/24. So remaining work after 8 days is (20/24 -7/24) =13/24.
When C joins after another 4 days, A, B and C can do (1/24 + 1/32+ 1/48) = 3/32 in 1 day. So, they need (32/3 * 13/24) = 52/9 days to complete the task.
This means, A works for a total of (4+4+52/9) days and in this he completes (4+4+52/9)*(1/24)=31/54 part of the whole task. So, A gets 10,800 * (31/54) = 6200.
I think choice D should be 6200.
Join the discussion

by Brent@GMATPrepNow » Sat Sep 07, 2013 10:18 am
vinni.k wrote:A, B and C working alone can complete a work in 24, 32, and 48 days respectively. "A" started the work and "B" joined him after 4 days and "C" joined them after 4 more days. If they were paid $10,800 for the work done, how much did "A" get ?

(A) 2800
(B) 3600
(C) 5400
(D) 6400
(E) 7600
Another approach is to assign the entire job a certain number of units.
Since the least common multiple of 24, 32 and 48 is 96, let's say that the entire job consists of 96 work units.

So, if A can complete the entire job (i.e., 96 work units) in 24 days, then A's rate is 4 units/day
Likewise, if B can complete the entire job (i.e., 96 work units) in 32 days, then B's rate is 3 units/day
And if C can complete the entire job in 48 days, then C's rate is 2 units/day

A works alone for 4 days. So, during this time, A completes 16 units of work.
This leaves us with 80 work units remaining (96 - 16 = 80)

A & B work together for 4 days. Their combined rate is 7 units/day (4+3=7). So, during this time, A+B complete 28 units of work.
This leaves us with 52 work units remaining (80 - 28 = 52)

A, B & C work together to complete job. Their combined rate is 9 units/day (4+3+2=9).
Since there are 52 work units remaining in the job, the number of days to complete the job = 52/9

IMPORTANT: 52/9 is not a nice number. However, since the answer choices are somewhat spread apart, I'm going to be somewhat aggressive with my estimation/rounding.

So, let's say that 52/9 = 6 (close enough).
This means that it takes A,B and C about 6 days to complete the rest of the job.

So, in total, A worked for approximately 14 days (4+4+6=14)
Since A works at a rate of 4 units/day, A completed a total of 56 work units (since 14x4=56).

The ENTIRE job was 96 work units. So, A did 56/96 of the work.
This means that A should get 56/96 of the $10,800 payment.
(56/96)(10,800) = (7/12)(10,800)
= $6300
Of course, none of the answer choices match $6300, but that's because we did some estimating/rounding earlier.
The closest answer choice is $6400, so the correct answer must be D

Cheers,
Brent
Brent Hanneson - Creator of GMATPrepNow.com
Image
Join the discussion

by vinni.k » Sat Sep 07, 2013 11:02 am
Thanks Brent. Your solution is crystal clear, and i also believe that the word "approx" must be mentioned here.

Vinni
Brent@GMATPrepNow wrote:
Another approach is to assign the entire job a certain number of units.
Since the least common multiple of 24, 32 and 48 is 96, let's say that the entire job consists of 96 work units.

So, if A can complete the entire job (i.e., 96 work units) in 24 days, then A's rate is 4 units/day
Likewise, if B can complete the entire job (i.e., 96 work units) in 32 days, then B's rate is 3 units/day
And if C can complete the entire job in 48 days, then C's rate is 2 units/day

A works alone for 4 days. So, during this time, A completes 16 units of work.
This leaves us with 80 work units remaining (96 - 16 = 80)

A & B work together for 4 days. Their combined rate is 7 units/day (4+3=7). So, during this time, A+B complete 28 units of work.
This leaves us with 52 work units remaining (80 - 28 = 52)

A, B & C work together to complete job. Their combined rate is 9 units/day (4+3+2=9).
Since there are 52 work units remaining in the job, the number of days to complete the job = 52/9

IMPORTANT: 52/9 is not a nice number. However, since the answer choices are somewhat spread apart, I'm going to be somewhat aggressive with my estimation/rounding.

So, let's say that 52/9 = 6 (close enough).
This means that it takes A,B and C about 6 days to complete the rest of the job.

So, in total, A worked for approximately 14 days (4+4+6=14)
Since A works at a rate of 4 units/day, A completed a total of 56 work units (since 14x4=56).

The ENTIRE job was 96 work units. So, A did 56/96 of the work.
This means that A should get 56/96 of the $10,800 payment.
(56/96)(10,800) = (7/12)(10,800)
= $6300
Of course, none of the answer choices match $6300, but that's because we did some estimating/rounding earlier.
The closest answer choice is $6400, so the correct answer must be D

Cheers,
Brent
Join the discussion

by GMATGuruNY » Sun Sep 08, 2013 7:15 am
The solution below is similar to Brent's, but with one suggestion:
To make the math easier, we can divide all of the times by 4:
A, B and C working alone can complete a work in 6, 8, and 12 days respectively. "A" started the work and "B" joined him after 1 day and "C" joined them after 1 more day. If they were paid $10,800 for the work done, how much did "A" get ?

(A) 2800
(B) 3600
(C) 5400
(D) 6200
(E) 7600
Let the job = the LCM of 6, 8 and 12 = 24 units.
Pay per unit = 10800/24 = $450.

A's rate = w/t = 24/6 = 4 units per day.
B's rate = w/t = 24/8 = 3 units per day.
C's rate = w/t = 24/12 = 2 units per day.

Work produced by A on the first day = 4 units.
Work produced by A on the second day = 4 units.
Work produced by B on the second day = 3 units.

Remaining work = 24-4-4-3 = 13 units.
When A, B and C work together, their combined rate = 4+3+2 = 9 units, of which 4 will be produced by A.
Thus, A will produces 4/9 of the remaining 13 units:
(4/9) * 13 = 52/9 ≈ 6.

Total number of units produced by A ≈ 4+4+6 = 14.
Thus:
A's pay ≈ 14*450 ≈ 6300.

The correct answer is D.

Please note that A's exact pay = $6200 (not $6400 as indicated in the problem as posted above):
(4 + 4 + 52/9) * 450 = 6200.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion