BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Work problem

Expert replies
by Veronica » Sat Sep 18, 2010 8:08 pm
15 programmers, working in a constant pace, finish a web page in 3 days. If after one day, 9 programmers quit, how many more days are needed to finish the remainder of the job?

a. 2; b.4; c.5; d.6; e.8

I solve this problem as follows:

15 programmers: 3 days: 1 web
-> 15 programmers: 1 day: 1/3 web
-> 15 programmers: 2 day: 2/3 web
-> 6 programmers: 5 day: 2/3 web

Therefore, 5-2 = 3 days more are needed to finish the remainder of the job

But in the answer key, no choice of 3, and the key is 5

Please show me whether I right, if not, what is my mistake??

Thank you!
Join the discussion
Source: — Problem Solving |

by HPengineer » Sat Sep 18, 2010 8:28 pm
There are some good solutions to this problem in the following post..

https://www.beatthegmat.com/java-guys-t55628.html

I like to solve these problems by multiplying the number of workers by the days it takes them to complete a job...

so for this problem 15 workers * 3 = 45 then because they say the 15 workers worked for 1 day we can take away 15.

So 45-15 now we have 30 items if you will to be completed by 6 workers... So 30/6 = 5
Join the discussion

by gmat1011 » Sat Sep 18, 2010 9:42 pm
I would set it up this way:

15 prog do 1/3 of the work in 1 day

1 prog does 1/3x15 = 1/45 of the work in 1 day


All 15 worked the first day so 15/45 of the work got done +> 1/3 of the work was done and 2/3 was left for the 2nd day onwards

But then 9 quit; so 6 prog had to do 2/3 of the work in how many more days after the first day to finish the remainder (2/3) of the job?

1/45 x 6 x D = 2/3

=> D = 2/18 x 45 = 5

If the question had been how many more days would be required to finish the job compared to the initial work plan or something to that effect then the answer would be 3; coz it took 6 days to finish the job (1+5) after 9 prog. left, in stead of just 3 days under the initial work plan when all 15 were working...
Join the discussion

by GMATGuruNY » Sun Sep 19, 2010 3:22 am
Veronica wrote:15 programmers, working in a constant pace, finish a web page in 3 days. If after one day, 9 programmers quit, how many more days are needed to finish the remainder of the job?

a. 2; b.4; c.5; d.6; e.8

I solve this problem as follows:

15 programmers: 3 days: 1 web
-> 15 programmers: 1 day: 1/3 web
-> 15 programmers: 2 day: 2/3 web
-> 6 programmers: 5 day: 2/3 web

Therefore, 5-2 = 3 days more are needed to finish the remainder of the job

But in the answer key, no choice of 3, and the key is 5

Please show me whether I right, if not, what is my mistake??

Thank you!
When the job is undefined, we can plug in our own value for the job. Plugging in our own value makes work problems much easier. Let's plug in that each programmer does 1 unit/day:

15 programmers = 15*1 = 15 units/day.
Over 3 days, 3*15 = 45 units. So job = 45.
After 1 day, 45-15 = 30 units left.
15-9 = 6 programmers left, so new rate is 6*1 = 6 units/day.
30/6 = 5 days.

The correct answer is C.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion