[spoiler]OA is B However could you please explain a fast way to go from t^2 +4t -672 = 0 to (t-24)(t+28) ? I spent a lot of time finding the two values 28 and 24, is there a fast way to factor?[/spoiler]
At his regular hourly rate, Don had estimated the labor cost of a repair job as $336 and he was paid that amount. However, the job took 4 hours longer than he had estimated and, consequently, he earned 2$ per hour less than his regular hourly rate. What was the time Don had estimated for the job, in hours?
28
24
16
14
12
[spoiler]OA is B However could you please explain a fast way to go from t^2 +4t -672 = 0 to (t-24)(t+28) ? I spent a lot of time finding the two values 28 and 24, is there a fast way to factor?[/spoiler]
Thanks.
At his regular hourly rate, Don had estimated the labor cost of a repair job as $336 and he was paid that amount. However, the job took 4 hours longer than he had estimated and, consequently, he earned 2$ per hour less than his regular hourly rate. What was the time Don had estimated for the job, in hours?
28
24
16
14
12
[spoiler]OA is B However could you please explain a fast way to go from t^2 +4t -672 = 0 to (t-24)(t+28) ? I spent a lot of time finding the two values 28 and 24, is there a fast way to factor?[/spoiler]
Thanks.