BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
Vote for Target Test Prep, Newsweek Readers’ Choice Awards 2026
NEWSWEEK READERS’ CHOICE 2026

BIG NEWS! Target Test Prep has been nominated, and they’d love your vote!

TTP has worked incredibly hard to build the best test prep experience possible, and winning Newsweek’s 2026 Readers’ Choice Award for Best Test Prep would mean a lot to them. If TTP has helped you, they’d be incredibly grateful for your vote. You can vote once each day through September 9.

Vote for TTP
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Machine R and S

Expert replies
by GmatKiss » Fri Nov 04, 2011 3:41 am
A company has two types of machines, type R and type S. Operating at a constant rate, a machine of type R does a certain job in 36 hours and a machine of type S does the same job in 18 hours. If the company used the same number of each type
of machine to do the job in 2 hours, how many machines of type R were used ?

A) 3
B) 4
C) 6
D) 9
E) 12
Join the discussion
Source: — Problem Solving |

by user123321 » Fri Nov 04, 2011 3:54 am
GmatKiss wrote:A company has two types of machines, type R and type S. Operating at a constant rate, a machine of type R does a certain job in 36 hours and a machine of type S does the same job in 18 hours. If the company used the same number of each type
of machine to do the job in 2 hours, how many machines of type R were used ?

A) 3
B) 4
C) 6
D) 9
E) 12
R does 1/36 th fraction of 1 job in an hour
S does 1/18 th fraction of that job in an hour
Both will do 1/36+1/18 th of job = 1/12th of job in an hour
=> they will do 1/6th of job in two hours
so if they have 6 machines of each one they will do the entire job in two hours.

hence 6 machines of R are required
Just started my preparation :D
Want to do it right the first time.
Join the discussion

by GMATGuruNY » Fri Nov 04, 2011 4:22 am
GmatKiss wrote:A company has two types of machines, type R and type S. Operating at a constant rate, a machine of type R does a certain job in 36 hours and a machine of type S does the same job in 18 hours. If the company used the same number of each type
of machine to do the job in 2 hours, how many machines of type R were used ?

A) 3
B) 4
C) 6
D) 9
E) 12
Let the job = 36 units.
Rate for machine R = 36/36 = 1 unit per hour.
Rate for machine S = 36/18 = 2 units per hour.
To complete the job in 2 hours, the number of units produced each hour = 36/2 = 18 units.
Since using one of each machine will produce 1+2 = 3 units per hour, and 18 units must be produced, we need 18/3 = 6 of each machine.

The correct answer is C.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by Anurag@Gurome » Fri Nov 04, 2011 4:27 am
GmatKiss wrote:A company has two types of machines, type R and type S. Operating at a constant rate, a machine of type R does a certain job in 36 hours and a machine of type S does the same job in 18 hours. If the company used the same number of each type
of machine to do the job in 2 hours, how many machines of type R were used ?

A) 3
B) 4
C) 6
D) 9
E) 12
In 1 hour, machine R does 1/36th of the job

In 1 hour, machine S does 1/18th of the job

In 1 hour, machine R and S together does 1/36 + 1/18 = 3/36 = 1/12th of the job or R + S together take 12 hours to do 1 job.

Now if the job is to be done in 2 hours, then we'll need 12/2 = 6 machines each.

The correct answer is C.
Anurag Mairal, Ph.D., MBA
GMAT Expert, Admissions and Career Guidance
Gurome, Inc.
1-800-566-4043 (USA)

Join Our Facebook Groups
GMAT with Gurome
https://www.facebook.com/groups/272466352793633/
Admissions with Gurome
https://www.facebook.com/groups/461459690536574/
Career Advising with Gurome
https://www.facebook.com/groups/360435787349781/
Join the discussion