A and B can complete a task in 20 days. B and C can complete the same task in 30 days. If A and C can complete the task in 40 days, arrange the efficiencies of A, B, and C in descending order.
$$A.\ A>B>C$$
$$B.\ A>C>B$$
$$C.\ B>A>C$$
$$D.\ B>C>A$$
$$E.\ C>A>B$$
The OA is C.
I don't have clear this PS question. I appreciate if any expert explains it to me. Thank you so much.
I think that I can solve it in the following way,
A and B complete the task in 20 days
B and C complete the task in 30 days
A and C complete the task in 40 day
I can see that B is fast than A and C, and also I can see that C is slower than B and A, hence the descending order for them will be, B > A > C.
$$A.\ A>B>C$$
$$B.\ A>C>B$$
$$C.\ B>A>C$$
$$D.\ B>C>A$$
$$E.\ C>A>B$$
The OA is C.
I don't have clear this PS question. I appreciate if any expert explains it to me. Thank you so much.
I think that I can solve it in the following way,
A and B complete the task in 20 days
B and C complete the task in 30 days
A and C complete the task in 40 day
I can see that B is fast than A and C, and also I can see that C is slower than B and A, hence the descending order for them will be, B > A > C.