If I'm reading this question correctly, the question is asking how many more hours should the men work to get the work done in 4 days assuming they work at the same pace as they did for the first 5 days.
I'm going to make the assumption that each man works the same amount. Over the course of 5 days, each man worked 8 hours per day or a total of 40 hours. In 40 hours of work per man, they completed 40% of the work. Therefore to complete the remaining 60% of the work, they have to complete 60 more hours of work.
60 hours spread across 4 days is an average of 15 hours per day.
The answer is E - 15 hours
Taking the GMAT Again...PhD this time!
October 2008 Score: GMAT - 750 (50 Q, 41 V)
Manhattan GMAT 1 - 11/20/11 - 750 (50 Q, 42 V)
Manhattan GMAT 2 - 12/3/11 - 780 (51 Q, 45 V)