64 men can complete a work in 9 days working for 8 hrs a day. After working for 5 days they notice that they have completed only 40% of the work, how many hours should the men work in the remaining 4 days so that they finish the work by the 9th day.
A) 9hrs
B) 10.5 hrs
C) 12 hrs
D) 14 hrs
E) 15 hrs
Time Work
This topic has expert replies
-
- Legendary Member
- Posts: 966
- Joined: Sat Jan 02, 2010 8:06 am
- Thanked: 230 times
- Followed by:21 members
-
- Master | Next Rank: 500 Posts
- Posts: 124
- Joined: Mon Jun 16, 2008 11:07 am
- Thanked: 21 times
- Followed by:14 members
- GMAT Score:750
If I'm reading this question correctly, the question is asking how many more hours should the men work to get the work done in 4 days assuming they work at the same pace as they did for the first 5 days.
I'm going to make the assumption that each man works the same amount. Over the course of 5 days, each man worked 8 hours per day or a total of 40 hours. In 40 hours of work per man, they completed 40% of the work. Therefore to complete the remaining 60% of the work, they have to complete 60 more hours of work.
60 hours spread across 4 days is an average of 15 hours per day.
The answer is E - 15 hours
I'm going to make the assumption that each man works the same amount. Over the course of 5 days, each man worked 8 hours per day or a total of 40 hours. In 40 hours of work per man, they completed 40% of the work. Therefore to complete the remaining 60% of the work, they have to complete 60 more hours of work.
60 hours spread across 4 days is an average of 15 hours per day.
The answer is E - 15 hours
Taking the GMAT Again...PhD this time!
October 2008 Score: GMAT - 750 (50 Q, 41 V)
Manhattan GMAT 1 - 11/20/11 - 750 (50 Q, 42 V)
Manhattan GMAT 2 - 12/3/11 - 780 (51 Q, 45 V)
October 2008 Score: GMAT - 750 (50 Q, 41 V)
Manhattan GMAT 1 - 11/20/11 - 750 (50 Q, 42 V)
Manhattan GMAT 2 - 12/3/11 - 780 (51 Q, 45 V)
- knight247
- Legendary Member
- Posts: 504
- Joined: Tue Apr 19, 2011 1:40 pm
- Thanked: 114 times
- Followed by:11 members
@cappyaa
Its said that they initially take 9 days to complete a work. So as per this by the 5th days end they should obviously have completed more than 50% of the work. Now if the problem says that after the 5th day they've only completed 40% it means that there was some other unforeseen delay which caused a lesser amount of work to be done. So we can't assume the rate to be based on the work done in these 5 days. Whats ur opinion?
Its said that they initially take 9 days to complete a work. So as per this by the 5th days end they should obviously have completed more than 50% of the work. Now if the problem says that after the 5th day they've only completed 40% it means that there was some other unforeseen delay which caused a lesser amount of work to be done. So we can't assume the rate to be based on the work done in these 5 days. Whats ur opinion?
-
- Master | Next Rank: 500 Posts
- Posts: 124
- Joined: Mon Jun 16, 2008 11:07 am
- Thanked: 21 times
- Followed by:14 members
- GMAT Score:750
That's why I think there is something missing with the wording of the problem. There needs to be another sentence in the question so you know what rate to use.
If you assume the original rate (72 hours to complete the work), after finishing 40%, they'd have completed 28.8 hours worth of work and will have 43.2 hours worth of work left to complete in 4 days. This would leave 10.8 hours of work per day left, which is not an answer choice.
I still do think we're supposed to assume that their rate is not as fast as originally said, but I agree that it's a poorly worded question.
If you assume the original rate (72 hours to complete the work), after finishing 40%, they'd have completed 28.8 hours worth of work and will have 43.2 hours worth of work left to complete in 4 days. This would leave 10.8 hours of work per day left, which is not an answer choice.
I still do think we're supposed to assume that their rate is not as fast as originally said, but I agree that it's a poorly worded question.
Taking the GMAT Again...PhD this time!
October 2008 Score: GMAT - 750 (50 Q, 41 V)
Manhattan GMAT 1 - 11/20/11 - 750 (50 Q, 42 V)
Manhattan GMAT 2 - 12/3/11 - 780 (51 Q, 45 V)
October 2008 Score: GMAT - 750 (50 Q, 41 V)
Manhattan GMAT 1 - 11/20/11 - 750 (50 Q, 42 V)
Manhattan GMAT 2 - 12/3/11 - 780 (51 Q, 45 V)
- gmatboost
- Master | Next Rank: 500 Posts
- Posts: 312
- Joined: Tue Aug 02, 2011 3:16 pm
- Location: New York City
- Thanked: 130 times
- Followed by:33 members
- GMAT Score:780
Yes, the wording makes no sense.
Apparently they can't...64 men can complete a work in 9 days working for 8 hrs a day.
how many hours should the men work in the remaining 4 days so that they finish the work by the 9th day
Greg Michnikov, Founder of GMAT Boost
GMAT Boost offers 250+ challenging GMAT Math practice questions, each with a thorough video explanation, and 100+ GMAT Math video tips, each 90 seconds or less.
It's a total of 20+ hours of expert instruction for an introductory price of just $10.
View sample questions and tips without signing up, or sign up now for full access.
Also, check out the most useful GMAT Math blog on the internet here.
GMAT Boost offers 250+ challenging GMAT Math practice questions, each with a thorough video explanation, and 100+ GMAT Math video tips, each 90 seconds or less.
It's a total of 20+ hours of expert instruction for an introductory price of just $10.
View sample questions and tips without signing up, or sign up now for full access.
Also, check out the most useful GMAT Math blog on the internet here.
-
- Legendary Member
- Posts: 966
- Joined: Sat Jan 02, 2010 8:06 am
- Thanked: 230 times
- Followed by:21 members
Well the OA is 15, so I am assuming that people do not work at the rate that was mentioned and hence failed to do work.
And as CappyAA mentioned, if they continue to work at their new rate(slower), it would take them 60hrs or 15 hrs a day to complete the work.
Terribly worded problem though.
And as CappyAA mentioned, if they continue to work at their new rate(slower), it would take them 60hrs or 15 hrs a day to complete the work.
Terribly worded problem though.