BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Mike, Mark...!

Expert replies
by chaitanya.bhansali » Thu Aug 07, 2014 10:06 am

Timer

00:00

Answers

A

B

C

D

E

Stats

Difficulty—

Mike, Mark and Matt can individually build a house in 12, 16 and 24 days respectively. If Mark starts building the house and receives help from Mike and Matt every second day, in how many days will they complete building the house?
A) 2 B) 4 C) 6 D) 8 E) 10
Join the discussion
Source: — Problem Solving |

by GMATGuruNY » Thu Aug 07, 2014 10:34 am
chaitanya.bhansali wrote:Mike, Mark and Matt can individually build a house in 12, 16 and 24 days respectively. If Mark starts building the house and receives help from Mike and Matt every second day, in how many days will they complete building the house?
A) 2 B) 4 C) 6 D) 8 E) 10
Let the house = 48 units.
Since Mike takes 12 days to build a house, Mike's rate = 48/12 = 4 units per day.
Since Mark takes 16 days to build a house, Mark's rate = 48/16 = 3 units per day.
Since Matt takes 24 days to build a hours, Matt's rate = 48/24 = 2 units.
When all 3 work together, their combined rate = 4+3+2 = 9 units per day.

Every 2 days:
Work produced by Mark alone on the first day = 3 units.
Work produced by all 3 on the second day = 9 units.
Thus:
Amount of work produced every 2 days = 3+9 = 12 units.

Since 12 units are produced every 2 days, the AVERAGE amount of work produced per day = 12/2 = 6 units.
At an average rate of 6 units per day, the time required to produce all 48 units = 48/6 = 8 days.

The correct answer is D.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by [email protected] » Thu Aug 07, 2014 11:04 am
Hi cahitanya.bhansali,

I'm a big fan of Mitch's approach to this question (converting the data and TESTing a Value). Since this is essentially just a "rate" question, you can organize the information in other ways and TEST THE ANSWERS.

We're given the length of time that it would take each person to build a house. I'm going to convert that information into the "fraction of a house" that each person could build per day:

Mike: 12 days = 1/12 of a house per day
Mark: 16 days = 1/16 of a house per day
Matt: 24 days = 1/24 of a house per day

We're told that MARK work every day, but that Mike and Matt only work every second day.

Looking at the answers (which are relatively small), and considering how little work each person does per day (or every second day, in the cases of Mike and Matt), to get 1 complete house, the answer has to be one of the larger options.

Let's TEST THE ANSWERS by starting with D. How much house would be built in 8 days?

Mark does 1/16 per day, so in 8 days he would complete 8/16 of the house.
Mike does 1/12 per day, so in 4 days he would complete 4/12 of the house.
Matt does 1/24 per day, so in 4 days he would complete 4/24 of the house.

8/16 + 4/12 + 4/24 =
1/2 + 1/3 + 1/6 =
3/6 + 2/6 + 1/6 = 1 complete house.

Final Answer: D

GMAT assassins aren't born, they're made,
Rich
Contact Rich at [email protected]
Image
Join the discussion

by shrivats » Thu Aug 07, 2014 8:41 pm
1) Mark alone completes 1/16 of the total work in one day
2) Three of the together complete 1/12 + 1/16 + 1/24 = 9/48 of the work in one day.

so of the first day mark alone works, 1/16 of the work will be completed.
and one second day if all three work together, 9/48 of the work will be completed.

So in two days, 1/16 + 9/48 = 12/48 = 1/4 of the work will be completed.

So the total work will be completed in 8 days.
Join the discussion

by shrivats » Thu Aug 07, 2014 9:03 pm
1) Mark alone completes 1/16 of the total work in one day
2) Three of the together complete 1/12 + 1/16 + 1/24 = 9/48 of the work in one day.

so of the first day mark alone works, 1/16 of the work will be completed.
and one second day if all three work together, 9/48 of the work will be completed.

So in two days, 1/16 + 9/48 = 12/48 = 1/4 of the work will be completed.

So the total work will be completed in 8 days.