Each of 10 machines works at a constant rate. When working together the amount of time it takes to complete a job is 16 hrs. How many hours will it take to complete the same job if only 8 machines work together?

18
20
22
24
26
Source: — Problem Solving |

User avatar
Master | Next Rank: 500 Posts
Posts: 316
Joined: Mon Sep 22, 2008 12:04 am
Thanked: 36 times
Followed by:1 members

Re: Work rate combination problem

by Morgoth » Wed Oct 01, 2008 6:34 pm
sethn23 wrote:Each of 10 machines works at a constant rate. When working together the amount of time it takes to complete a job is 16 hrs. How many hours will it take to complete the same job if only 8 machines work together?

18
20
22
24
26
rate * time * no. of machines = work

rate * 16 * 10 = 1

rate = 1/160

rate * time * no. of machines = work

1/160*time*8= 1

time = 160/8 = 20.

Hope this helps.

Junior | Next Rank: 30 Posts
Posts: 14
Joined: Wed Oct 01, 2008 5:59 pm

by sethn23 » Wed Oct 01, 2008 6:38 pm
thanks again Morgoth

Newbie | Next Rank: 10 Posts
Posts: 9
Joined: Tue Jun 10, 2008 11:34 am

by allechat » Thu Oct 02, 2008 12:38 pm
could you also look at this as, # of machines is reduced by 1/5, so it's going to take 1/5 more time?

20 is 1/5 more time than 16.

change formula: (10-8)/10 machines= 1/5 fewer machines

then (x-16)/x=1/5, 5x-80=x
5x=x+80, x=20

Junior | Next Rank: 30 Posts
Posts: 25
Joined: Fri Jan 23, 2009 11:57 am
Location: Minneapolis
Thanked: 1 times

Very simple formula

by peddisetty » Sun Feb 15, 2009 3:39 pm
You can use M1D1W2 = M2D2W1.

So, here its M1D1 = M2D2 => 10*16 = 8*x

x = 20.

Very simple........
Raj Peddisetty

User avatar
Master | Next Rank: 500 Posts
Posts: 319
Joined: Wed Feb 04, 2009 10:32 am
Location: Delhi
Thanked: 84 times
Followed by:9 members

by sureshbala » Tue Feb 17, 2009 7:59 pm
Since 10 machines take 16 hrs, it is clear that the work takes 160 machine hours. Since now we have 8 machines, to contribute those 160 machine hours, time taken is 160/8 = 20.

The same thing is explained above in the form of a forumula

Junior | Next Rank: 30 Posts
Posts: 27
Joined: Sat Feb 07, 2009 6:14 pm
Location: Las Vegas, NV
Thanked: 7 times
Followed by:1 members
GMAT Score:760

Re: Work rate combination problem

by griscomtestprep » Wed Feb 18, 2009 12:23 am
sethn23 wrote:Each of 10 machines works at a constant rate. When working together the amount of time it takes to complete a job is 16 hrs. How many hours will it take to complete the same job if only 8 machines work together?

18
20
22
24
26
Since there are 8/10 of the machines, it is going to take 10/8 as long.
10/8 * 16 = 20
Free Hour of Live Online GMAT Training
Griscom Test Prep
www.griscomtestprep.net
[email protected]
702-406-7688

Master | Next Rank: 500 Posts
Posts: 117
Joined: Wed Jun 09, 2010 7:02 am

by missrochelle » Wed Aug 25, 2010 9:07 pm
sethn23 wrote:Each of 10 machines works at a constant rate. When working together the amount of time it takes to complete a job is 16 hrs. How many hours will it take to complete the same job if only 8 machines work together?

18
20
22
24
26
What are you supposed to recognize in this problem that states the total time is 160hrs? I assumed each machine worked 1/16 hr which is wrong...