A, B and C, each of them working alone can complete a job in 6, 8 and 12 days respectively. If all three of them work together to complete a job and earn $2340, what will be C's share of the earnings?
(A) $520
(B) $630
(C) $1000
(D) $1080
(E) $1170
(A) $520
(B) $630
(C) $1000
(D) $1080
(E) $1170