Together, 15 type A machines and 7 type B machines can complete a certain job in 4 hours.
Together 8 type B machines and 15 type C machines can complete the same job in 11 hours.
How many hours would it take one type A machine, one type B machine, and one type C machine working together to complete the job (assuming constant rates for each machine)?
(A) 22 hours
(B) 30 hours
(C) 44 hours
(D) 60 hours
(E) It cannot be determined from the information above.
[spoiler]OA=C[/spoiler]
Source: Veritas Prep
Together 8 type B machines and 15 type C machines can complete the same job in 11 hours.
How many hours would it take one type A machine, one type B machine, and one type C machine working together to complete the job (assuming constant rates for each machine)?
(A) 22 hours
(B) 30 hours
(C) 44 hours
(D) 60 hours
(E) It cannot be determined from the information above.
[spoiler]OA=C[/spoiler]
Source: Veritas Prep