Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Work Time Problem

Expert replies
by coolhabhi » Fri Nov 25, 2016 10:24 am
The ratio of the number of days taken to complete a work by A,B,C is 6:3:2. Working together they complete a work in 20 days. If B left the work before 2 days and C left before 4 days to completion, in how many would the work be completed then?

a) 21(1/3) days
b) 21(2/3) days
c) 22(1/3) days
d) 22(2/3) days
e) 23 days

OE: D
Join the discussion
Source: — Problem Solving |

by DavidG@VeritasPrep » Fri Nov 25, 2016 11:24 am
coolhabhi wrote:The ratio of the number of days taken to complete a work by A,B,C is 6:3:2. Working together they complete a work in 20 days. If B left the work before 2 days and C left before 4 days to completion, in how many would the work be completed then?

a) 21(1/3) days
b) 21(2/3) days
c) 22(1/3) days
d) 22(2/3) days
e) 23 days

OE: D
Let's say that A's rate is "x."
Because B takes half as many days to complete the job, we know that B's rate should be double A's. So call B's rate '2x.'
Because C takes 1/3 as many days to complete the job, we know that C's rate should be triple A's. So call C's rate '3x.'

The combined rate is x + 2x + 3x = 6x. We know that together, they can complete a job in 20 days, so their combined rate is 1 job/20 days or 1/20. If 6x = 1/20, then x = 1/120.

A's rate = x = 1/120
B's rate = 2x = 1/60
C's rate = 3x = 1/40

Let's say A works for T days. B will work for (T - 2) days and C will work for (T - 4) days
Amount of work performed by each

A: (1/120) * T
B: (1/60) * (T-2)
C: (1/40) * (T-4)

(1/120)T + (1/60)(T-2) + (1/40)(T - 4) = 1 job

Multiply through by 120

T + 2(T-2) + 3(T - 4) = 120
T + 2T-4 + 3T -12 = 120
6T -16 = 120
6T = 136
T = 136/6 = 22 2/3; Answer is D
Veritas Prep | GMAT Instructor

Veritas Prep Reviews
Save $100 off any live Veritas Prep GMAT Course
Join the discussion

by GMATGuruNY » Fri Nov 25, 2016 3:21 pm
coolhabhi wrote:The ratio of the number of days taken to complete a work by A,B,C is 6:3:2. Working together they complete a work in 20 days. If B left the work before 2 days and C left before 4 days to completion, in how many would the work be completed then?

a) 21(1/3) days
b) 21(2/3) days
c) 22(1/3) days
d) 22(2/3) days
e) 23 days
Let the time ratio be applied to a job of 6 widgets.
If A takes 6 days to complete this job, A's rate = w/t = 6/6 = 1 widget per day.
If B takes 3 days to complete this job, B's rate = w/t = 6/3 = 2 widgets per day.
If C takes 2 days to complete this job, C's rate = w/t = 6/2 = 3 widgets per day.

Combined rate for A, B and C = 1+2+3 = 6 widgets per day.
Thus, the actual job = the amount of work produced by A, B and C in 20 days = (combined rate for A, B and C)(20 days) = 6*20 = 120 widgets.

Since C leaves 4 days early and B leaves 2 days early, A and B work together without C for 2 days, while A works alone for the last 2 days.
Amount of work produced by A and B in 2 days = (combined rate for A and B)(2 days) = (1+2)(2) = 6 widgets.
Amount of work produced by A in the last 2 days = (A's rate)(2 days) = 1*2 = 2 widgets.

Remaining work = 120 - 6 - 2 = 112 widgets.
The remaining work is produced by A, B and C working together.
Time for A, B and C to produce 112 widgets = w/(combined rate for A, B and C) = 112/6 = 56/3 days = 18 2/3 days.
Total time = (time when A, B and C all work together) + (time when A and B work together without C) + (time when A works alone) = (18 2/3) + 2 + 2 = 22 2/3 days.

The correct answer is D.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.