Work Problem

This topic has expert replies
Senior | Next Rank: 100 Posts
Posts: 33
Joined: Thu Apr 15, 2010 9:36 pm
Thanked: 1 times

Work Problem

by shrey2287 » Wed Aug 29, 2012 7:59 am
Mac can finish a job in M days and Jack can finish the same job in J days. After working together for T days, Mac left and Jack alone worked to complete the remaining work in R days. If Mac and Jack completed an equal amount of work, how many days would have it taken Jack to complete the entire job working alone?

(1) M = 20 days
(2) R = 10 days

A. Statement (1) ALONE is sufficient, but Statement (2) ALONE is not sufficient
B. Statement (2) ALONE is sufficient, but Statement (1) ALONE is not sufficient
C. BOTH statements TOGETHER are sufficient, but NEITHER statement ALONE is sufficient
D. EACH statement ALONE is sufficient
E. Statements (1) and (2) TOGETHER are NOT sufficient

User avatar
MBA Admissions Consultant
Posts: 2279
Joined: Fri Nov 11, 2011 7:51 am
Location: New York
Thanked: 660 times
Followed by:266 members
GMAT Score:770

by Jim@StratusPrep » Wed Aug 29, 2012 8:26 am
The setup for these problems is output/time:

1/M + 1/J = 1/(Total Time)

1) Insufficient: You have no idea Jack's speed nor can you calculate it without The total time or R
2) Insufficient: The speed of both Jack and Mac can vary with this information

Together, you know that Mac can do the job in 20 days and that Jack takes 10 days to finish the remaining work. However, you do not know the amount of the remaining work, because you do not know how long Mac and Jack worked together, which would tell you their respective rates.
GMAT Answers provides a world class adaptive learning platform.
-- Push button course navigation to simplify planning
-- Daily assignments to fit your exam timeline
-- Organized review that is tailored based on your abiility
-- 1,000s of unique GMAT questions
-- 100s of handwritten 'digital flip books' for OG questions
-- 100% Free Trial and less than $20 per month after.
-- Free GMAT Quantitative Review

Image

User avatar
MBA Admissions Consultant
Posts: 2279
Joined: Fri Nov 11, 2011 7:51 am
Location: New York
Thanked: 660 times
Followed by:266 members
GMAT Score:770

by Jim@StratusPrep » Wed Aug 29, 2012 8:26 am
BTW, the answer is thus E.
GMAT Answers provides a world class adaptive learning platform.
-- Push button course navigation to simplify planning
-- Daily assignments to fit your exam timeline
-- Organized review that is tailored based on your abiility
-- 1,000s of unique GMAT questions
-- 100s of handwritten 'digital flip books' for OG questions
-- 100% Free Trial and less than $20 per month after.
-- Free GMAT Quantitative Review

Image

User avatar
Community Manager
Posts: 1060
Joined: Fri May 13, 2011 6:46 am
Location: Utrecht, The Netherlands
Thanked: 318 times
Followed by:52 members

by neelgandham » Wed Aug 29, 2012 8:34 am
Mac can finish the job in M days. So, in one day Mac can complete 1/M th of the Job.
Jack can finish the job in J days. So, in one day Jack can complete 1/J th of the Job.
Mac + Jack can complete 1/M + 1/J th of the Job in a day.
After working together for T days, Mac + Jack can complete T*(1/M + 1/J)th of the work.
Jack alone completed R/J th of the job.

So, T*(1/M + 1/J) + R/J = 1
Total work done by Jack = T/J + R/J
Total work done by Mac = T/M
Total work done by Jack = Total work done by Mac
T/J + R/J = T/M

Now, the question can be rephrased to, If T/M + T/J + R/J = 1 and T/J + R/J = T/M, then what is the value of J?'
(1)M = 20 days
T/M + T/J + R/J = 1
T/J + R/J = T/M
So, T/M + T/M = 1
2T = M = 20. T = 10.
We know T/J + R/J = T/M, 10/J + R/J = 10/20. Since we don't know the value of R, statement I is insufficient to answer the question.
(2)R = 10 days
T/M + T/J + R/J = 1
T/J + R/J = T/M
So, 2*(T/J + R/J) = 1
T/J + R/J = 1/2
T/J + 10/J = 1/2. Since we don't know the value of T, statement II is insufficient to answer the question.
From I and II
T/J + 10/J = 1/2 and M = 20. T = 10. So, 10/J + 10/J = 1/2 and J = 40. Eureka!

Answer C
Anil Gandham
Welcome to BEATtheGMAT | Photography | Getting Started | BTG Community rules | MBA Watch
Check out GMAT Prep Now's online course at https://www.gmatprepnow.com/

User avatar
Master | Next Rank: 500 Posts
Posts: 167
Joined: Fri Mar 09, 2012 8:35 pm
Thanked: 39 times
Followed by:3 members

by adthedaddy » Wed Aug 29, 2012 8:48 am
I would solve this as follows:

Let Mac finish the job in M days. Thus, his rate = 1/M
Let Jack finish the job in J days. His rate = 1/J

Now, Mac leaves after working together for 'T' days and for the remaining R days Jack worked to complete the entire job.

Thus, we conclude that Mac worked for 'T' days and Jack worked for 'T+R' days.
Also, it is given that both did equal amount of work

Thus, part of job Mac did T*(1/M) = T/M ........ (1)
and Jack did (T+R)(1/J) = (T+R)/J .............. (2)

As both of them did equal amount of work, from eqn(1) above T/M = 1/2 => T= M/2 .....(3)
and from eqn(2) above, (T+R)/J = 1/2 => (T+R)= J/2 => T = J/2 - R ...................(4)

Compare value of 'T' from eqns(3) & (4), we get

M/2 = J/2 - R

We make Jack 'J' as subject of the eqn as we have to find 'the no of days Jack takes to complete the job'.

Thus, J = 2R + M .........................(5)

Now, from the question, Option(1) gives M=20 days
Eqn(5) gives us J=2R + 20
Not Sufficient as we cannot solve this eqn.

Option (2) gives R=10 days.
Not sufficient as J=20 + M does not solve the eqn.

Taking both the options together, we can substitute the value of M & R in eqn(5),
Thus we get,
J = 20 + 20 = 40 days

SUFFICIENT

[spoiler]Ans: (C)[/spoiler]
"Your time is limited, so don't waste it living someone else's life. Don't be trapped by dogma - which is living with the results of other people's thinking. Don't let the noise of others' opinions drown out your own inner voice. And most important, have the courage to follow your heart and intuition. They somehow already know what you truly want to become. Everything else is secondary" - Steve Jobs