[GMAT math practice question]
There are 4 machines with the same work rate. If it took k hours for 3 machines to work and did k-2 hours for 4 machines when working together, what is the value of k?
A. 4
B. 5
C. 6
D. 7
E. 8
There are 4 machines with the same work rate. If it took k
This topic has expert replies
- Max@Math Revolution
- Elite Legendary Member
- Posts: 3991
- Joined: Fri Jul 24, 2015 2:28 am
- Location: Las Vegas, USA
- Thanked: 19 times
- Followed by:37 members
Math Revolution
The World's Most "Complete" GMAT Math Course!
Score an excellent Q49-51 just like 70% of our students.
[Free] Full on-demand course (7 days) - 100 hours of video lessons, 490 lesson topics, and 2,000 questions.
[Course] Starting $79 for on-demand and $60 for tutoring per hour and $390 only for Live Online.
Email to : [email protected]
-
- Senior | Next Rank: 100 Posts
- Posts: 94
- Joined: Tue Dec 16, 2014 9:50 am
- Location: London, UK
- Thanked: 2 times
- Followed by:4 members
- GMAT Score:770
Total machine working hours will be the same for 3 machines and 4 machines.Max@Math Revolution wrote:[GMAT math practice question]
There are 4 machines with the same work rate. If it took k hours for 3 machines to work and did k-2 hours for 4 machines when working together, what is the value of k?
A. 4
B. 5
C. 6
D. 7
E. 8
Total machine hours with 3 machines = 3k
Total machine hours with 4 machines = 4(k-2)
3k = 4(k-2)
3k = 4k - 8
k = 8
Answer = (E) 8
- Max@Math Revolution
- Elite Legendary Member
- Posts: 3991
- Joined: Fri Jul 24, 2015 2:28 am
- Location: Las Vegas, USA
- Thanked: 19 times
- Followed by:37 members
=>
Work Amount = Number of machines * Work Rate * Time
If r is the machine's work rate, we have 3rk = 4r(k-2) or 3k = 4k -8.
Thus k = 8.
Therefore, E is the answer.
Answer: E
Work Amount = Number of machines * Work Rate * Time
If r is the machine's work rate, we have 3rk = 4r(k-2) or 3k = 4k -8.
Thus k = 8.
Therefore, E is the answer.
Answer: E
Math Revolution
The World's Most "Complete" GMAT Math Course!
Score an excellent Q49-51 just like 70% of our students.
[Free] Full on-demand course (7 days) - 100 hours of video lessons, 490 lesson topics, and 2,000 questions.
[Course] Starting $79 for on-demand and $60 for tutoring per hour and $390 only for Live Online.
Email to : [email protected]
GMAT/MBA Expert
- Scott@TargetTestPrep
- GMAT Instructor
- Posts: 7294
- Joined: Sat Apr 25, 2015 10:56 am
- Location: Los Angeles, CA
- Thanked: 43 times
- Followed by:29 members
Let the rate of each machine be r. We can create the equation:Max@Math Revolution wrote:[GMAT math practice question]
There are 4 machines with the same work rate. If it took k hours for 3 machines to work and did k-2 hours for 4 machines when working together, what is the value of k?
A. 4
B. 5
C. 6
D. 7
E. 8
(3r)k = (4r)(k - 2)
3k = 4k - 8
8 = k
Answer: E