Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Twenty-four men can complete a work in sixteen days.Thirty

Expert replies
by BTGmoderatorDC » Sat Sep 08, 2018 10:59 pm
Timer
00:00
Your answer
Difficulty–

right wrong

Pick an answer to see how members did

Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54

OA B

Source: Veritas Prep
Join the discussion
Source: — Problem Solving |

by GMATGuruNY » Sun Sep 09, 2018 3:11 am
BTGmoderatorDC wrote:Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54
Let the rate for each man = 1 widget per day, implying that the rate for 24 men = 24 widgets per day.
Since 24 men complete the job in 16 days, the total amount of work = rt = 24*16 widgets.

Since 32 women require 24 days, the rate for 32 women = w/t = (24*16)/24 = 16 widgets per day.
Since 32 women produce 16 widgets per day, the rate for each woman = (daily output)/(number of women) = 16/32 = 1/2 widget per day.
Thus, the combined rate for 16 men and 16 women = (16*1) + (16 * 1/2) = 24 widgets per day.

In 12 days, the amount of work produced by 16 men and 16 women = rt = 24*12 widgets.
Remaining work = (total work) - (work produced in the first 12 days) = (24*16) - (24*12) = 24(16-12) = 24*4 = 96 widgets.

To complete the remaining work in 2 days, the required rate = (remaining work)/(number of days) = 96/2 = 48 widgets per day.
Since the rate must increase from the value in red to the value in blue -- an increase of 24 widgets per day -- 24 more men are required.

The correct answer is B.

It seems sexist to make the rate for each man twice that for each woman.
Official problems strive to avoid this sort of bias.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

BTGmoderatorDC wrote:Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54
Nice problem!

Let´s suppose each man does 1 task/day , and each woman does k tasks/day (where k>0, not necessarily an integer).

By the question stem, we know that:

> 24 men do 1 work in 16 days, hence 1 work = 24*16 tasks (1)
> 32 women do 1 work in 24 days, hence 1 work = 32*24*k tasks implies, by (1) above, that k = 1/2

> 16 men and 16 women will do in 12 days exactly 16*12*1 + 16*12*1/2 = 24*12 tasks, therefore by (1) we have still 24*(16-12) = 24*4 tasks to be done.

> If x is the number of men to be added (our FOCUS), we have a group of (16+x) men and 16 women performing (16+x)*1 + 16*1/2 = (24+x) tasks/day , and the final touch is done
with UNITS CONTROL, one of our method´s most powerful tools:

\[24 \cdot 4\,\,\,{\text{tasks}}\,\,\, = \,\,2\,\,days\,\,\left( {\frac{{24 + x\,\,\,{\text{tasks}}}}{{1\,\,\,{\text{day}}}}\,\,\,\begin{array}{*{20}{c}}
\nearrow \\
\nearrow
\end{array}} \right)\,\,\,\,\,\, \Rightarrow \,\,\,\,\,24 + x = 24 \cdot 2\,\,\,\,\, \Rightarrow \,\,\,\,\,\,? = x = 24\]
Obs.: arrows indicate licit converters.

(If you realize this solution is absolutely clear and safe, you are the perfect candidate for our method... try our free and super-complete test drive!)

This solution follows the notations and rationale taught in the GMATH method.

Regards,
fskilnik.
Fabio Skilnik :: GMATH method creator ( Math for the GMAT)
English-speakers :: https://www.gmath.net
Portuguese-speakers :: https://www.gmath.com.br
Join the discussion

by Scott@TargetTestPrep » Mon Sep 17, 2018 5:32 pm
BTGmoderatorDC wrote:Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54
Since 24 men can complete a work in 16 days, the rate of 24 men is 1/16, and hence the rate of 1 man is (1/16)/24 = 1/384.

Similarly, 32 women can complete the same work in 24 days, so the rate of 32 women is 1/24, and hence the rate of 1 woman is (1/24)/32 = 1/768.

Thus, the rate for 16 men and 16 women is 16 x (1/384) + 16 x (1/768) = 1/24 + 1/48 = 2/48 + 1/48 = 3/48 = 1/16.

Since these 16 men and 16 women worked for 12 days, they completed (1/16) x 12 = 12/16 = 3/4 of the job.

Thus, 1/4 of the job is left to be done. To find the number of additional men needed to complete the remaining work in 2 days, we can let n = the additional men needed and create the following equation (keep in mind that the rate of each man is 1/384 and the rate of the existing 16 men and 16 women is 1/16):

n(1/384)(2) + (1/16)(2) = 1/4

n/192 + 1/8 = 1/4

n/192 = 1/8

8n = 192

n = 24

Alternate Solution:

If 24 men can do the job in 16 days, then 16 men, which is 2/3 of 24 men, can do the job in 16/(2/3) = 24 days.

Similarly, since 32 women can do the same job in 24 days, 16 women, which is half of 32 women, can do the same job in 24/(1/2) = 48 days.

Thus, in one day, 1/24 of the job is done by men and 1/48 of the job is done by women; thus 1/24 + 1/48 = 3/48 = 1/16 of the job is done in total. Therefore, with 16 men and 16 women working, the job will be finished in 16 days. Since 16 men and 16 women have already worked for 12 days, the remaining job would have been completed by 16 men and 16 women in 16 - 12 = 4 days.

Since 16 men complete the job in exactly half the time compared to 16 women, the men work twice as fast as women; i.e. 1 man can do the same job done by 2 women. Thus, the work done by 16 men and 16 women is equivalent to the work done by 16 + 16/2 = 24 men.

Now, if we want the remaining job to be completed in 2 days instead of 4; in other words, if we want the remaining job to be completed in half the time, we should double the number of men. Since 16 men and 16 women is equivalent to 24 men, we should add 24 more men to get the remaining job done in 2 days.

Answer: B

Scott Woodbury-Stewart
Founder and CEO
[email protected]

Image

See why Target Test Prep is rated 5 out of 5 stars on BEAT the GMAT. Read our reviews

ImageImage
Join the discussion