A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working
on the project together and A quits 10 days before the project is completed, in how many days will the project be
completed?
A. 18 days
B. 27 days
C. 26.67 days
D. 16 days
E. 12 days
Time and work
This topic has expert replies
-
- Senior | Next Rank: 100 Posts
- Posts: 64
- Joined: Sat Aug 01, 2009 3:13 am
- Thanked: 5 times
- Followed by:1 members
- GMAT Score:740
- Morgoth
- Master | Next Rank: 500 Posts
- Posts: 316
- Joined: Mon Sep 22, 2008 12:04 am
- Thanked: 36 times
- Followed by:1 members
A's rate = 1/20mohitsharda wrote:A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working
on the project together and A quits 10 days before the project is completed, in how many days will the project be
completed?
A. 18 days
B. 27 days
C. 26.67 days
D. 16 days
E. 12 days
B's rate = 1/30
combine rate of A and B = 1/20 + 1/30 = 1/12
A and B can complete the entire work in 12 days
A quits 10 days before the work can be completed, this means A and B together worked for 2 days [12-10]
In 2 days A and B together completed = 2 * 1/12 = 1/6 of the total work
Work still needs to be completed = 1 -1/6 = 5/6
5/6 work will be completed by B alone = 5/6 / 1/30 = 25
Therefore, the work can be completed in 2+25 days = 27 days
Hence B.
Hope this helps.
Answer is B. If they were working together they would have completed the project in 12 days. However since A quit in 2 days we have 25/30th of the project that needs to be completed by B alone which will take 25 days. hence (A+B) + B = 2+25 or 27 days.
-
- Senior | Next Rank: 100 Posts
- Posts: 87
- Joined: Sat Feb 28, 2009 7:01 am
- Location: India
- Thanked: 2 times
@ morgoth,
I think answer is A.
Since its written that A left 10 days before the project is completed, so during this time B worked alone. ie. 10/30=1/3 of the work is completed by B during last 10 days and 2/3rd of the work is completed by both A and B together which took 8 days.
i.e total of 8+10=18 days.
pls correct if I am wrong.
anyways whats the OA
I think answer is A.
Since its written that A left 10 days before the project is completed, so during this time B worked alone. ie. 10/30=1/3 of the work is completed by B during last 10 days and 2/3rd of the work is completed by both A and B together which took 8 days.
i.e total of 8+10=18 days.
pls correct if I am wrong.
anyways whats the OA
-
- Master | Next Rank: 500 Posts
- Posts: 338
- Joined: Fri Apr 17, 2009 1:49 am
- Thanked: 9 times
- Followed by:3 members
-
- Newbie | Next Rank: 10 Posts
- Posts: 6
- Joined: Tue Jul 14, 2009 7:28 am
- Location: India
-
- Legendary Member
- Posts: 527
- Joined: Mon Jun 02, 2008 9:14 am
- Location: Atlanta
- Thanked: 17 times
I got A as well.
Rate of A = 1/20, Rate of B = 1/30
Let the total time be T.
from the question
(T - 10)* (1/20) + T * (1/30) = 1
gives T = 18 days
Rate of A = 1/20, Rate of B = 1/30
Let the total time be T.
from the question
(T - 10)* (1/20) + T * (1/30) = 1
gives T = 18 days
-
- Legendary Member
- Posts: 527
- Joined: Mon Jun 02, 2008 9:14 am
- Location: Atlanta
- Thanked: 17 times
I got A as well.
Rate of A = 1/20, Rate of B = 1/30
Let the total time be T.
from the question
(T - 10)* (1/20) + T * (1/30) = 1
gives T = 18 days
Rate of A = 1/20, Rate of B = 1/30
Let the total time be T.
from the question
(T - 10)* (1/20) + T * (1/30) = 1
gives T = 18 days
-
- Master | Next Rank: 500 Posts
- Posts: 150
- Joined: Thu May 05, 2011 10:04 am
- Thanked: 5 times
- Followed by:4 members
@pandeyvineet
Rate of A = 1/20, Rate of B = 1/30
Let the total time be T.
from the question
(T - 10)* (1/20) + T * (1/30) = 1
gives T = 18 days
The highlighted text should be 1/12 coz. A and B work together for the first two days.
So the answer will be 27 days.
Rate of A = 1/20, Rate of B = 1/30
Let the total time be T.
from the question
(T - 10)* (1/20) + T * (1/30) = 1
gives T = 18 days
The highlighted text should be 1/12 coz. A and B work together for the first two days.
So the answer will be 27 days.
- sl750
- Master | Next Rank: 500 Posts
- Posts: 496
- Joined: Tue Jun 07, 2011 5:34 am
- Thanked: 38 times
- Followed by:1 members
Rate of A =1/20. Rate of B=1/30
Combined rate of A and B = 1/20+1/30 = 1/12
Entire work completed by both A and B in 12 days
As A leaves 10 days before that means, A and B worked together for the first 2 days
In 2 days, together they completed 2/12 = 1/6
Remaining work to be completed by B is 5/6
Time taken by B is 5/6/1/30 = 25
Total completion time is 25+2 = 27
Combined rate of A and B = 1/20+1/30 = 1/12
Entire work completed by both A and B in 12 days
As A leaves 10 days before that means, A and B worked together for the first 2 days
In 2 days, together they completed 2/12 = 1/6
Remaining work to be completed by B is 5/6
Time taken by B is 5/6/1/30 = 25
Total completion time is 25+2 = 27
- knight247
- Legendary Member
- Posts: 504
- Joined: Tue Apr 19, 2011 1:40 pm
- Thanked: 114 times
- Followed by:11 members
@sl750 and msr4mba. Your answers are wrong. Check this link
https://www.beatthegmat.com/a-quits-befo ... t=New-York
Both Mitch and Anurag have solved it.
Here is my solution:
Let the work to be done be the typing of 60 pages
A
Time=20days
Rate=60/20= 3pages/Day
B
Time=30days
Rate=60/30=2pages/Day
Now let the time for which B works equal x i.e. from the beginning to end. The work done by B is 2x (Work=Rate*Time). Since A quit 10 days prior to the end the time he worked for is
x-10 so the work done by him is 3(x-10)
Work Done by A+Work Done by B=60
2x+3x-30=60
x=18
Hence A
https://www.beatthegmat.com/a-quits-befo ... t=New-York
Both Mitch and Anurag have solved it.
Here is my solution:
Let the work to be done be the typing of 60 pages
A
Time=20days
Rate=60/20= 3pages/Day
B
Time=30days
Rate=60/30=2pages/Day
Now let the time for which B works equal x i.e. from the beginning to end. The work done by B is 2x (Work=Rate*Time). Since A quit 10 days prior to the end the time he worked for is
x-10 so the work done by him is 3(x-10)
Work Done by A+Work Done by B=60
2x+3x-30=60
x=18
Hence A
- GMATGuruNY
- GMAT Instructor
- Posts: 15539
- Joined: Tue May 25, 2010 12:04 pm
- Location: New York, NY
- Thanked: 13060 times
- Followed by:1906 members
- GMAT Score:790
For those who got 27 days:
If A leaves 10 days before the job is completed, it is not possible that B works for 25 days after A leaves.
The two times (10 days and 25 days) contradict each other.
To guarantee that B works for exactly 10 days on his own, first determine how much work B completes in 10 days.
Then calculate how much time is needed for A and B to complete the remaining work.
This problem is no different from the following:
B works alone for 10 days.
Then A and B work together to complete the job.
What is the total number of days that B works?
I posted a solution here:
https://www.beatthegmat.com/a-quits-befo ... t=New-York.
If A leaves 10 days before the job is completed, it is not possible that B works for 25 days after A leaves.
The two times (10 days and 25 days) contradict each other.
To guarantee that B works for exactly 10 days on his own, first determine how much work B completes in 10 days.
Then calculate how much time is needed for A and B to complete the remaining work.
This problem is no different from the following:
B works alone for 10 days.
Then A and B work together to complete the job.
What is the total number of days that B works?
I posted a solution here:
https://www.beatthegmat.com/a-quits-befo ... t=New-York.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.
As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.
For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.
As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.
For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
- Abhishek009
- Master | Next Rank: 500 Posts
- Posts: 359
- Joined: Wed Mar 11, 2009 4:37 am
- Location: Kolkata, India
- Thanked: 50 times
- Followed by:2 members
Let the total work be of 60 units ( LCM of the Time Taken by A & B)mohitsharda wrote:A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working
on the project together and A quits 10 days before the project is completed, in how many days will the project be
completed?
A. 18 days
B. 27 days
C. 26.67 days
D. 16 days
E. 12 days
Efficiency of A is 3 units
Efficiency of B is 2 units
Together the produce 5 units
Let A and B works together for ' d ' days
So together the complete 5d units of work
B does the rest of the work ( ie for 10 days ) , so work done by B is 20 units
Now 5d + 20 = 60
So 5d = 40
and d = 8
Hence A and B worked for 8 days and B alone worked for 10 days , they worked 18 days in all....
Abhishek