Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

In anticipation of a flood

Expert replies
by ritumaheshwari02 » Thu Nov 29, 2012 9:03 am
In anticipation of a flood, a city engineer estimated that it would take 15 hours for a crew of 40 workers to build a dike 20 meters long around one of the city’s wells. Using the same estimate of worker-hours per meter of dike, how many workers would be needed to build a similar dike 25 meters long around another well, if the dike needs to be completed in 6 hours?

A. 56
B. 60
C. 80
D. 100
E. 125
Join the discussion
Source: — Problem Solving |

by Bill@VeritasPrep » Thu Nov 29, 2012 10:44 am
I think you can pretty easily knock out a couple of answers. A 20m dike takes 15 hours to complete when 40 workers are building it, and we need a longer dike in less than HALF the time. If we're going to cut time by over 50%, we need to increase rate by over 100% to make up for it, and the only way we can increase the rate of building is by adding more workers. We can eliminate A, B, and C.

We need 15*40 = 600 worker-hours to complete 20m. 25m is 25% greater than 20m, so we'll need 25% more worker hours to complete the new project. 1.25 * 600 = 750. Divide 750 worker-hours by 6 actual hours to see that we need 125 workers to complete the dike.
Join Veritas Prep’s 2010 Instructor of the Year, Matt Douglas for GMATT Mondays

Visit the Veritas Prep Blog

Try the FREE Veritas Prep Practice Test
Join the discussion

by GMATGuruNY » Thu Nov 29, 2012 12:23 pm
ritumaheshwari02 wrote:In anticipation of a flood, a city engineer estimated that it would take 15 hours for a crew of 40 workers to build a dike 20 meters long around one of the city’s wells. Using the same estimate of worker-hours per meter of dike, how many workers would be needed to build a similar dike 25 meters long around another well, if the dike needs to be completed in 6 hours?

A. 56
B. 60
C. 80
D. 100
E. 125
Let the rate for each worker = 1 unit per hour.
Rate for 40 workers = 40 units per hour.
In 15 hours, the amount of work produced = 40*15 = 600 units.
Thus, the 20-meter dike is equal to 600 units of work.

To determine the number of units that need to be produced in order to build a 25-meter dike, set up a proportion:
20 meters/600 units = 25 meters/x units
1/30 = 25/x
x = 750 units.

To produce 750 units in 6 hours, the required rate = 750/6 = 125 units per hour.
Since each worker produces 1 unit per hour, the number of workers required = 125.

The correct answer is E.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion