3 men, 4 women and 6 children can complete a work in 7 days. A woman does double the work a man does and a child does half the work a man does. How many women alone can complete this work in 7 days?

A 7
B 8
C 12
D 15
E none of these

Legendary Member
Posts: 2898
Joined: Thu Sep 07, 2017 2:49 pm
Thanked: 6 times
Followed by:5 members

by Vincen » Mon Jun 11, 2018 12:59 am
Hello.

We know that the job can be completed in 7 days when there are working

- 3 M (men)
- 4 W (women)
- 6 C (children)

Also, we know that "a woman does double the work a man does", hence $$W=2M\ \ \ \Rightarrow\ \ \ \ M=\frac{W}{2}$$ and "a child does half the work a man does", hence $$C=\frac{M}{2}\ \ \ \Rightarrow\ \ \ \ C=\frac{\frac{W}{2}}{2}=\frac{W}{4}.$$ Then, the job can be completed in 7 days when there are working

- 3M =(3/2)W.
- 4W
- 6C= (6/4)W=(3/2)W

If we sum these quantities we will get that there are needed 7 women to complete the job in 7 days.

Therefore, the correct answer is the option A.

I hope it is clear enough.

User avatar
GMAT Instructor
Posts: 15539
Joined: Tue May 25, 2010 12:04 pm
Location: New York, NY
Thanked: 13060 times
Followed by:1906 members
GMAT Score:790

by GMATGuruNY » Mon Jun 11, 2018 2:16 am
vaibhav101 wrote:3 men, 4 women and 6 children can complete a work in 7 days. A woman does double the work a man does and a child does half the work a man does. How many women alone can complete this work in 7 days?

A 7
B 8
C 12
D 15
E none of these
Let the rate for each child = 1 unit per day.
Since each child does half the work of a man, the rate for each man = 2 units per day.
Since each woman does double the work of a man, the rate for each woman = 4 units per day.

Combined rate for 3 men, 4 women and 6 children = (3*2) + (4*4) + (6*1) = 28 units per day.
Over 7 days, the amount of work produced by 3 men, 4 women and 6 children = rt = 7*28 units.

To complete the job in 7 days, the required rate = w/t = (7*28)/7 = 28 units per day.
Since each woman produces 4 units per day, the number of women required to produce 28 units per day = 28/4 = 7.

The correct answer is A.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3

GMAT/MBA Expert

User avatar
GMAT Instructor
Posts: 16207
Joined: Mon Dec 08, 2008 6:26 pm
Location: Vancouver, BC
Thanked: 5254 times
Followed by:1268 members
GMAT Score:770

by Brent@GMATPrepNow » Mon Jun 11, 2018 4:38 am
vaibhav101 wrote:3 men, 4 women and 6 children can complete a work in 7 days. A woman does double the work a man does and a child does half the work a man does. How many women alone can complete this work in 7 days?

A 7
B 8
C 12
D 15
E none of these
Starting point: 3 men, 4 women and 6 children

A child does half the work a man does.
In other words, 1 child = 1/2 a man
This means 6 children = 3 men
So, let's just REPLACE the 6 children with 3 men to get: 6 men and 4 women

A woman does double the work a man does
In other words, 1 man = 1/2 a woman
This means 6 men = 3 women
So, let's just REPLACE the 6 men with 3 women to get: 7 women

Answer: A

Cheers,
Brent
Brent Hanneson - Creator of GMATPrepNow.com
Image

GMAT/MBA Expert

User avatar
GMAT Instructor
Posts: 1462
Joined: Thu Apr 09, 2015 9:34 am
Location: New York, NY
Thanked: 39 times
Followed by:22 members

by Jeff@TargetTestPrep » Wed Jun 13, 2018 3:37 pm
vaibhav101 wrote:3 men, 4 women and 6 children can complete a work in 7 days. A woman does double the work a man does and a child does half the work a man does. How many women alone can complete this work in 7 days?

A 7
B 8
C 12
D 15
E none of these
We can let the rate of a man = m, the rate of a woman = 2m, and the rate of a child = (1/2)m, thus:

3m + 4(2m) + 6[(1/2)m] = 1/7

3m + 8m + 3m = 1/7

14m = 1/7

m = 1/98

So the rate of a woman = 2/98 = 1/49 of the job per day.

Thus, in 7 days, a woman can complete 7 x 1/49 = 1/7 of the job. So if there are 7 women, they can complete 7 x 1/7 = 1 entire job.

Alternate Solution:

Since a child does half the work a man does, the work done by 3 men, 4 women and 6 children is equivalent to the work done by 3 + 6/2 = 6 men and 4 women. Since a woman does twice the work a man does, the work done by 6 men and 4 women is equivalent to the work done by 6/2 + 4 = 7 women. So, 7 women can complete the job in 7 days.

Answer: A