BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

another work problem

Expert replies
by ace_gre » Thu Feb 04, 2010 1:15 am
Deep and Ana decided to work together & complete the construction of a road.However, as Deep went out of town, Ana started work alone and finished 1/4 th of the road and took 'x' days more than what they would have taken if they worked together. After this, Ana fell ill and Deep working alone, completed the construction of 1/3 of the remaining road and took 25/16 x days more than what they would have taken if they had worked together.Finally both of them worked together and completed the remaining road the whole process taking a total of 121 days.
In how many days can deep alone complete the construction of entire road?
1. 180 days
2. 194
3. 160

Sorry no OA and taken from another forum. Please help solve. Thanks!
Join the discussion
Source: — Problem Solving |

by ajith » Thu Feb 04, 2010 2:11 am
ace_gre wrote:Deep and Ana decided to work together & complete the construction of a road.However, as Deep went out of town, Ana started work alone and finished 1/4 th of the road and took 'x' days more than what they would have taken if they worked together. After this, Ana fell ill and Deep working alone, completed the construction of 1/3 of the remaining road and took 25/16 x days more than what they would have taken if they had worked together.Finally both of them worked together and completed the remaining road the whole process taking a total of 121 days.
In how many days can deep alone complete the construction of entire road?
1. 180 days
2. 194
3. 160

Sorry no OA and taken from another forum. Please help solve. Thanks!
Say Deep alone can finish the work in d days and Ana alone can finish the work in a days

for finishing 1/4 ana would take a/4 days . Combined they would take ad/(a+d) days to finish the work and hence to complete 1/4, they will have to work together for ad/4(a+d) days

now; x = a/4 - ad/4(a+d) --------(1)
Similarly 25/16x = d/3 - ad/3(a+d) -----------(2)

The work left =1-(1/4+1/3) = 5/12
time taken to complete the work = 5/12(ad/(a+d))

The total time taken = a/4+d/3 + 5/12(ad/(a+d)) =121

(1)+(2) => x+25/16x = a/4+d/3 -7/12 (ad/(a+d))

=> 41x/16 =a/4+d/3 + 5/12(ad/(a+d)) - ad/(a+d)
41x/16 = 121 - ad/(a+d)
ad/(a+d) =121-41x/16

x= a/4 - (121-41x/16)/4 -----(5)
25x/16 = d/3 - (121-41x/16)/3 ---------(6)

I give up .... I cant solve this
Always borrow money from a pessimist, he doesn't expect to be paid back.
Join the discussion

by Ian Stewart » Thu Feb 04, 2010 12:37 pm
ace_gre wrote:Deep and Ana decided to work together & complete the construction of a road.However, as Deep went out of town, Ana started work alone and finished 1/4 th of the road and took 'x' days more than what they would have taken if they worked together. After this, Ana fell ill and Deep working alone, completed the construction of 1/3 of the remaining road and took 25/16 x days more than what they would have taken if they had worked together.Finally both of them worked together and completed the remaining road the whole process taking a total of 121 days.
In how many days can deep alone complete the construction of entire road?
1. 180 days
2. 194
3. 160

Sorry no OA and taken from another forum. Please help solve. Thanks!
This problem is completely absurd; there is no way to solve it without some kind of computational assistance. If I saw it on a real GMAT, I'd try to find a shortcut: presumably x needs to be an integer, and so does (25/16)x, so my first assumption would be that x is divisible by 16. Since x needs to be quite small here (since the entire process only takes 121 days), I'd guess that x=16 and proceed from there. On a real GMAT question, that would almost certainly lead to the correct answer, but here that doesn't work.

You can do the problem algebraically as follows: we know that if they worked together the entire time, they would have saved x + (25/16)x days, or (41/16)x days. So

A+D do 1 job in 121 - (41/16)x days
A does 1/4 job in (121 - (41/16)x)/4 + x days --> A does 1 job in 121 - (41/16)x + 4x = 121 + (23/16)x days
D does 1/3 job in (121 - (41/16)x)/3 + (25/16)x days --> D does 1 job in 121 - (41/16)x + (75/16)x = 121 + (34/16)x days

Summarizing:

A+D do 1 job in 121 - (41/16)x days
A does 1 job in 121 + (23/16)x days
D does 1 job in 121 + (34/16)x days

You can then plug these values into the rates formula, but this produces an absolutely ridiculous quadratic equation, and the only way to get an answer is with a calculator. In the end, you find that x is approximately 17.555, that Deep takes roughly 158.3 days alone, that Ana takes roughly 146.2 days alone, and that together they would take roughly 76 days. You'd never see a question like this on the real GMAT.
For online GMAT math tutoring, or to buy my higher-level Quant books and problem sets, contact me at ianstewartgmat at gmail.com

ianstewartgmat.com
Join the discussion