BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

A paint crew gets a rush order to paint 80 houses in a new d

Expert replies
by BTGmoderatorDC » Fri Feb 01, 2019 5:37 am

Timer

00:00

Answers

A

B

C

D

E

Stats

Difficulty

A paint crew gets a rush order to paint 80 houses in a new development. They paint the first y houses at a rate of x houses per week. Realizing that they'll be late at this rate, they bring in some more painters and paint the rest of the houses at the rate of 1.25x houses per week. The total time it takes them to paint all the houses under this scenario is what fraction of the time it would have taken if they had painted all the houses at their original rate of x houses per week?

(A) 0.8(80 - y)
(B) 0.8 + 0.0025y
(C) 80/y - 1.25
(D) 80/1.25y
(E) 80 - 0.25y

OA B

Source: Official Guide
Join the discussion
Source: — Problem Solving |

by GMATGuruNY » Fri Feb 01, 2019 6:26 am
BTGmoderatorDC wrote:A paint crew gets a rush order to paint 80 houses in a new development. They paint the first y houses at a rate of x houses per week. Realizing that they'll be late at this rate, they bring in some more painters and paint the rest of the houses at the rate of 1.25x houses per week. The total time it takes them to paint all the houses under this scenario is what fraction of the time it would have taken if they had painted all the houses at their original rate of x houses per week?

(A) 0.8(80 - y)
(B) 0.8 + 0.0025y
(C) 80/y - 1.25
(D) 80/1.25y
(E) 80 - 0.25y
Let y=0, implying that NONE of the 80 houses are painted at the original rate of x houses per week, with the result that ALL 80 houses are painted at the greater rate of (5/4)x houses per week.

The total time it takes them to paint all the houses under this scenario is what fraction of the time it would have taken if they had painted all the houses at their original rate?
Time and rate have a RECIPROCAL RELATIONSHIP.
Since the rate for painting all 80 houses is 5/4 the original rate, the time for painting all 80 houses is 4/5 of the original time.

The correct answer must yield 4/5 when y=0.
Only B works:
0.8 + 0.0025y = 0.8 = 4/5.

The correct answer is B.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by swerve » Fri Feb 01, 2019 7:49 am
original time = 80/x weeks
new time = y/x + (80-y)/1.25x
ratio=y/x + (80-y)/1.25x : 80/x = 1.25y+80 - y:100 = 0.25y+80:100
ratio = 0.8 0.0025y
Join the discussion

by [email protected] » Fri Feb 01, 2019 2:37 pm
Hi All,

We're told that a paint crew gets a rush order to paint 80 houses in a new development. They paint the first Y houses at a rate of X houses per week. Realizing that they'll be late at this rate, they bring in some more painters and paint the rest of the houses at the rate of 1.25X houses per week. We're asked to find the total time it takes them to paint all the houses under this scenario as a fraction of the time it would have taken if they had painted all the houses at their original rate of X houses per week. This question can be solved in a number of different ways, including by TESTing VALUES (and the answer choices are written in such a way that you don't have to do too much math overall to answer the question).

To start, we should choose a value for X that will work well with 1.25X. Let's choose X = 4 (so 1.25X = 5). In addition, we should look to choose a value for Y that will leave a remaining number of house that will be a multiple of 5...

Let's TEST...
X = 4
Y = 20

For the first 20 houses, painting 4 houses/week will take 20/4 = 5 weeks.
For the remaining 60 houses, painting 5 houses/week will take 60/5 = 12 weeks.
Total time = 5 + 12 = 17 weeks

At the original rate, the 80 houses would take 80/4 = 20 weeks.

Thus, we're looking for a fraction that equals 17/20 = .85.... notice how that answer is a number that is LESS than 1. Considering how the answer choices are written, and that our Y = 20, you should be able to eliminate all of the wrong answers without doing too much math...

Answer A: (.8)(60) --> greater than 1
Answer B: (.8) + a tiny decimal --> exactly what we're looking for!
Answer C: 80/20 - 1.25 --> a little less than 3
Answer D: (80)/(1.25)(20) = 80/25 --> greater than 1
Answer E: (80) - (.25)(20) --> greater than 1

Final Answer: B